16432 W SEPTO ST 91343

Certificate Information: 16432 W SEPTO ST 91343

Application / Permit
21014-20000-06065
Plan Check / Job No.
B21VN16820
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
20'-8" X 23'-4" ADDITION OF MASTER BEDROOM AND CLOSET, AND REMOVE AND REPLACE THE (E) PATIO COVER WITH A NEW 15' X 25' PATIO COVER TO (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 2/3/2022
Issuing Office
Current Status
CofO Issued on 8/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2021 APPLICANT
Assigned to Plan Check Engineer 12/10/2021 SERGIO MUNIZ
Corrections Issued 12/11/2021 SERGIO MUNIZ
Applicant returned to address corrections 12/31/2021 SERGIO MUNIZ
Plan Check Approved 1/6/2022 SERGIO MUNIZ
Building Plans Picked Up 1/25/2022 APPLICANT
Issued 2/3/2022 APPLICANT
CofO in Progress 6/20/2023 JAVIER RAMOS JR
Permit Finaled 8/30/2023 RUBEN SALAS
CofO Issued 8/30/2023 RUBEN SALAS
Permit Finaled 8/30/2023 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/16/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/20/2021 CARLOS AGUILERA
Grading Pre-Inspection Cleared 12/20/2021 ALEXANDER ANDREWS

Contact Information

Contractor Owner-Builder       ,
Engineer Yu,, Jennifer Arianna; Lic. No.: C79156 3828 EARLE AVE      ROSEMEAD, CA 91770

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/25/2022 Not Ready for Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 10/25/2022 No Access for Inspection JAVIER RAMOS JR
Pre-Inspection 10/25/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 11/9/2022 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 11/9/2022 Approved JAVIER RAMOS JR
Insulation 11/9/2022 Partial Approval JAVIER RAMOS JR
Deputy Wood Construction 12/29/2022 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 1/6/2023 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 1/6/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 1/26/2023 Approved JAVIER RAMOS JR
HVAC-Rough 1/26/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 1/26/2023 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Approved JOHN COLEMAN
Insulation 1/31/2023 Approved JOHN COLEMAN
Drywall Nailing 2/15/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/7/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Final 6/7/2023 Approved JAVIER RAMOS JR
Final 6/7/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 6/7/2023 Approved JAVIER RAMOS JR
Green Building Rough 6/7/2023 Approved JAVIER RAMOS JR
HVAC-Final 6/7/2023 Approved JAVIER RAMOS JR
PLUMBING-Final 6/7/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/7/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 6/7/2023 Approved JAVIER RAMOS JR
Final 6/20/2023 OK to Issue CofO JAVIER RAMOS JR