9535-9537 N REMICK AVE 91331

Certificate Information: 9535-9537 N REMICK AVE 91331

Application / Permit
21014-20000-06060
Plan Check / Job No.
B21VN16817
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT A PORTION OF THE (E) CARPORT AND THE (E) DWELLING TO AN ACCESSORY DWELLING UNIT (ADU) PER LAMC 12.22 A.33(c) AND (e) AND ADDITION TO CREATE AN IRREGULAR 29.75' x 31.83' TO THE ADU.
Permit Issued
Issued on 11/16/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2022 APPLICANT
Assigned to Plan Check Engineer 1/19/2022 LUIS RINCON
Corrections Issued 1/22/2022 LUIS RINCON
Applicant returned to address corrections 4/11/2022 LUIS RINCON
Plan Check Approved 5/10/2022 LUIS RINCON
Building Plans Picked Up 7/5/2022 APPLICANT
Issued 11/16/2022 APPLICANT
CofO in Progress 3/15/2024 MATTHEW NELSON
Permit Finaled 3/29/2024 DANIEL ORRANTE
CofO Issued 3/29/2024 DANIEL ORRANTE
Permit Finaled 3/29/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/15/2022 JARED ABEGG
Roof/Waste drainage to street Cleared 2/15/2022 JARED ABEGG
Eng Process Fee Ord 176,300 Cleared 2/24/2022 JARED ABEGG
Sewer availability Cleared 2/24/2022 JARED ABEGG

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/17/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/6/2023 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 4/6/2023 Corrections Issued MICHEL ABAJAN
PLUMBING-Rough 4/11/2023 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 6/1/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 6/1/2023 Partial Approval CHRISTOPHER DELLEFIELD
MERV13>=Rough 6/1/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Partial Approval MICHEL ABAJAN
Gas Test 8/1/2023 Not Ready for Inspection MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 8/10/2023 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 8/25/2023 Corrections Issued MICHEL ABAJAN
Gas Test 8/25/2023 Approved MICHEL ABAJAN
Green Building Rough 8/25/2023 Not Ready for Inspection MICHEL ABAJAN
MERV13>=Rough 8/25/2023 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 8/25/2023 Partial Approval MICHEL ABAJAN
Gas Test 9/5/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 9/14/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 9/20/2023 Approved MICHEL ABAJAN
Green Building Rough 9/20/2023 Approved MICHEL ABAJAN
HVAC-Rough 9/20/2023 Approved MICHEL ABAJAN
Pre-Inspection 9/20/2023 Partial Approval MICHEL ABAJAN
Insulation 10/12/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/12/2023 Not Ready for Inspection MICHEL ABAJAN
Drywall Nailing 11/9/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 2/20/2024 Approved MICHEL ABAJAN
HVAC-Final 2/20/2024 Approved MICHEL ABAJAN
PLUMBING-Final 2/20/2024 Approved MICHEL ABAJAN
Final 3/14/2024 OK to Issue CofO MATTHEW NELSON
Green Building Final 3/14/2024 Approved MATTHEW NELSON
MERV13>=Final 3/14/2024 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/14/2024 SGSOV Approved MATTHEW NELSON
Smoke Detectors 3/14/2024 Approved MATTHEW NELSON
Service/Power Release 3/15/2024 Approved MATTHEW NELSON