13868 W TERRA BELLA ST 91331
Certificate Information: 13868 W TERRA BELLA ST 91331
- Application / Permit
- 21014-20000-06050
- Plan Check / Job No.
- B21VN16785
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET GARAGE AND ADD IRR. SHAPED 34'-10" X 36'-4" FOR (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(B). ALL WORK PER WFPP; “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 4/21/2022
- Issuing Office
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2021 | JENNIFER LEE |
| Corrections Issued | 12/22/2021 | JENNIFER LEE |
| Building Plans Picked Up | 12/23/2021 | APPLICANT |
| Applicant returned to address corrections | 4/4/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 4/20/2022 | SEAN SHAHMIRI |
| Issued | 4/21/2022 | APPLICANT |
| CofO in Progress | 2/25/2024 | GREGG CUMMINGS |
| Permit Finaled | 3/29/2024 | DANIEL ORRANTE |
| CofO Issued | 3/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/11/2022 | AMIR KASHFI |
| Roof/Waste drainage to street | Cleared | 2/11/2022 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2022 | AMIR KASHFI |
| Private sewage disp. approval | Cleared | 2/16/2022 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/25/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 7/29/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Deputy Drilled-In Anchors | 8/12/2022 | Conditional Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 8/16/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/16/2022 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/14/2022 | Not Ready for Inspection | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2022 | Partial Approval | DAVID MATSON |
| Gas Test | 9/14/2022 | Approved | DAVID MATSON |
| HVAC-Rough | 9/14/2022 | Approved | DAVID MATSON |
| PLUMBING-Rough | 9/14/2022 | Partial Approval | DAVID MATSON |
| Interior/Exterior Lathing | 9/19/2022 | Approved | WILLIAM WREN |
| Shower Pan | 9/19/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 9/22/2022 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 10/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 10/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 10/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 10/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 10/12/2022 | Corrections Issued | GREGG CUMMINGS |
| Drywall Nailing | 10/13/2022 | Corrections Issued | WILLIAM WREN |
| Drywall Nailing | 10/20/2022 | Approved | WILLIAM WREN |
| Pre-Inspection | 2/27/2023 | Approved | GREGG CUMMINGS |
| Final | 5/24/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 5/24/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 5/24/2023 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 5/24/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 7/7/2023 | Corrections Issued | GREGG CUMMINGS |
| Smoke Detectors | 7/7/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 2/23/2024 | Approved | GREGG CUMMINGS |
| Final | 2/23/2024 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 2/23/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 2/23/2024 | Approved | GREGG CUMMINGS |