8321-8323 N BARDWELL AVE 91402

Certificate Information: 8321-8323 N BARDWELL AVE 91402

Application / Permit
21014-20000-06045
Plan Check / Job No.
B21VN16780
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE (E) ATTACHED GARAGE TO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (e) AND AN ADDITION OF 14'1" x 17'7" TO THE ADU. DESIGN PER WFPP.
Permit Issued
Issued on 12/23/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2022 APPLICANT
Assigned to Plan Check Engineer 1/19/2022 LUIS RINCON
Corrections Issued 1/22/2022 LUIS RINCON
Applicant returned to address corrections 2/28/2022 LUIS RINCON
Applicant returned to address corrections 3/2/2022 LUIS RINCON
Plan Check Approved 3/28/2022 LUIS RINCON
No Progress 3/28/2022 LUIS RINCON
Plan Check Approved 3/28/2022 LUIS RINCON
Building Plans Picked Up 4/6/2022 APPLICANT
Plan Check Approved 10/6/2022 LUIS RINCON
Issued 12/23/2022 APPLICANT
CofO in Progress 7/23/2024 VINCENT HANLEY
CofO Issued 8/6/2024 RUBEN SALAS
Permit Finaled 8/6/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/28/2022 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/28/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/7/2022 LEE GUILBEAUX
Sewer availability Cleared 2/7/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/1/2023 No Access for Inspection GREGG CUMMINGS
Pre-Inspection 2/6/2023 Approved GREGG CUMMINGS
Underground Mechanical 2/17/2023 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 3/2/2023 Corrections Issued GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 3/6/2023 Approved GREGG CUMMINGS
Footing/Foundation/Slab 3/6/2023 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 4/18/2023 Corrections Issued GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 4/24/2023 Partial Approval WILLIAM WREN
ELECTRICAL-Rough 6/9/2023 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 6/9/2023 Partial Approval GREGG CUMMINGS
Green Building Rough 6/9/2023 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 6/9/2023 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 6/9/2023 Approved GREGG CUMMINGS
Underground Mechanical 6/9/2023 Partial Approval GREGG CUMMINGS
Interior/Exterior Lathing 6/15/2023 Approved MATTHEW NELSON
BUILDING-Rough-Frame 6/26/2023 Approved GREGG CUMMINGS
Green Building Rough 6/26/2023 Approved GREGG CUMMINGS
HVAC-Rough 6/26/2023 Approved GREGG CUMMINGS
Insulation 7/5/2023 Corrections Issued GREGG CUMMINGS
Shower Pan 7/5/2023 Corrections Issued GREGG CUMMINGS
Insulation 9/5/2023 Approved CHRISTOPHER ROJAS
Shower Pan 9/5/2023 Approved CHRISTOPHER ROJAS
Drywall Nailing 9/12/2023 Approved GREGG CUMMINGS
Final 6/28/2024 Corrections Issued GREGG CUMMINGS
Green Building Final 6/28/2024 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 6/28/2024 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 6/28/2024 Approved GREGG CUMMINGS
ELECTRICAL-Final 7/22/2024 Approved VINCENT HANLEY
Final 7/22/2024 OK to Issue CofO VINCENT HANLEY
Green Building Final 7/22/2024 Approved VINCENT HANLEY
Green Building Rough 7/22/2024 Approved VINCENT HANLEY
HVAC-Final 7/22/2024 Approved VINCENT HANLEY
PLUMBING-Final 7/22/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/22/2024 SGSOV Approved VINCENT HANLEY