13414 W LOCHRIN LANE 91342

Certificate Information: 13414 W LOCHRIN LANE 91342

Application / Permit
21014-20000-06040
Plan Check / Job No.
B21VN16757
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 5'-11" x 60'-8" ADDITION TO EXTEND BEDROOMS AND BATHROOMS AND 22'-2" x 1'-3" ADDITION TO EXTEND DINING ROOM AND KITCHEN. FIRE DAMAGE REPAIR AND INTERIOR REMODEL TO THE (E) SINGLE FAMILY DWELLING TO ADD A FULL BATHROOM, AND CONVERT STORAGE TO A LAUNDRY ROOM AND A HALF BATHROOM . " NFPA-13D FIRE SPRINKLERS THRU-OUT"
Permit Issued
Issued on 3/21/2022
Issuing Office
Current Status
CofO Issued on 1/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2021 APPLICANT
Assigned to Plan Check Engineer 1/6/2022 SARKIS HARABEDIAN
Corrections Issued 1/12/2022 SARKIS HARABEDIAN
Quality Review Completed 1/19/2022 STEVEN KIM
Building Plans Picked Up 1/20/2022 APPLICANT
Plan Check Approved 3/21/2022 SARKIS HARABEDIAN
Issued 3/21/2022 APPLICANT
CofO in Progress 7/2/2024 KEVIN BERBERYAN
CofO in Progress 7/2/2024 KEVIN BERBERYAN
CofO in Progress 1/16/2025 KEVIN BERBERYAN
Permit Finaled 1/28/2025 RUBEN SALAS
CofO Issued 1/28/2025 RUBEN SALAS
Permit Finaled 1/28/2025 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/12/2022 SARKIS HARABEDIAN
Eng Process Fee Ord 176,300 Cleared 2/23/2022 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 2/23/2022 LEE GUILBEAUX
Hydrant and Access approval Cleared 3/11/2022 CINDY JOSSELYN

Contact Information

Contractor Owner-Builder       ,
Engineer Papazyan,, Andranik; Lic. No.: C56824 635 W COLORADO ST STE 104      GLENDALE, CA 91204

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/22/2022 Corrections Issued JOHN HAYES
Pre-Inspection 4/26/2022 Partial Approval JOHN HAYES
Deputy Drilled-In Anchors 8/2/2022 Conditional Approval ARAM AVEDISIAN
PLUMBING-Rough 8/12/2022 Partial Approval CALEB MEISTER
Sewer 8/12/2022 Approved CALEB MEISTER
Excavation/Setback/Form/Re-Bar 8/31/2022 Corrections Issued ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 9/7/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/16/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 4/12/2023 No Access for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 4/18/2023 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 4/18/2023 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 4/18/2023 Conditional Approval ARAM AVEDISIAN
HVAC-Rough 4/18/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 4/18/2023 Approved ARAM AVEDISIAN
Deputy Wood Construction 4/21/2023 Conditional Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 5/15/2023 Approved ARAM AVEDISIAN
Green Building Rough 5/15/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 5/15/2023 Partial Approval ARAM AVEDISIAN
Verify Sprinkler Sign Off 5/15/2023 Approved ARAM AVEDISIAN
Insulation 5/23/2023 Approved ARAM AVEDISIAN
Drywall Nailing 5/26/2023 Approved CHRISTOPHER DELLEFIELD
Shower Pan 6/13/2023 Approved THOMAS FINNILA
HVAC-Rough 7/18/2023 No Access for Inspection ROBERT GOLD
ELECTRICAL-Final 6/4/2024 Not Ready for Inspection KEVIN BERBERYAN
Final 6/4/2024 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 6/4/2024 Approved KEVIN BERBERYAN
Green Building Final 6/4/2024 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Final 6/4/2024 Approved KEVIN BERBERYAN
PLUMBING-Final 6/4/2024 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 6/4/2024 SGSOV Not Required KEVIN BERBERYAN
Smoke Detectors 6/4/2024 Approved KEVIN BERBERYAN
Final 6/24/2024 Partial Approval KEVIN BERBERYAN
Green Building Final 6/24/2024 Approved KEVIN BERBERYAN
Service/Power Release 1/13/2025 Approved KEVIN BERBERYAN
Final 1/16/2025 OK to Issue CofO KEVIN BERBERYAN