21021-21023 W STRATHERN ST 91304

Certificate Information: 21021-21023 W STRATHERN ST 91304

Application / Permit
21014-20000-06039
Plan Check / Job No.
B21VN16756
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
21'-9" X 5'-9" IRREG SHAPED GROUND FLOOR ADDITION, 22'-2" X 24'-1" SECOND STORY ADDITION, AND CONVERT 5'-2" X 8'-10" PORTION OF DWELLING AND ATTACHED GARAGE TO ACCESSORY DWELLING UNIT (906 SQ FT) PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 2/24/2022
Issuing Office
Current Status
Issued on 2/24/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/3/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 JEROME MAGAT PALMA
Corrections Issued 12/16/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 1/19/2022 TSE MING HUANG
Plan Check Approved 2/24/2022 JEROME MAGAT PALMA
Issued 2/24/2022 APPLICANT
Building Plans Picked Up 2/28/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/21/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/21/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/21/2021 CARLOS AGUILERA
Sewer availability Cleared 12/21/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/16/2022 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 5/16/2022 Not Ready for Inspection STEVEN BACK
Pre-Inspection 5/16/2022 Partial Inspection STEVEN BACK
Excavation/Setback/Form/Re-Bar 5/31/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 6/13/2022 Partial Approval STEVEN BACK
Insulation 6/13/2022 Corrections Issued STEVEN BACK
PLUMBING-Rough 6/13/2022 Partial Approval STEVEN BACK
Insulation 6/17/2022 Partial Approval STEVEN BACK
PLUMBING-Rough 6/17/2022 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/24/2022 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 7/15/2022 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/15/2022 Partial Approval STEVEN BACK
Deputy Wood Construction 8/3/2022 Conditional Approval STEVEN BACK
ELECTRICAL-Rough 9/2/2022 Corrections Issued SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 9/2/2022 Corrections Issued SEAN WIRCH
Green Building Rough 9/2/2022 Not Ready for Inspection SEAN WIRCH
HVAC-Rough 9/2/2022 Corrections Issued SEAN WIRCH
PLUMBING-Rough 9/2/2022 Corrections Issued SEAN WIRCH
Shower Pan 9/2/2022 Approved SEAN WIRCH
Deputy Wood Construction 9/7/2022 Conditional Approval JESUS PINEDA
ELECTRICAL-Rough 9/12/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 Corrections Issued STEVEN BACK
PLUMBING-Rough 9/12/2022 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 9/28/2022 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/28/2022 Approved STEVEN BACK
Green Building Rough 9/28/2022 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 9/28/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 11/2/2022 Approved STEVEN BACK
Green Building Rough 11/2/2022 Approved STEVEN BACK
HVAC-Rough 11/2/2022 Approved STEVEN BACK
Interior/Exterior Lathing 11/2/2022 Partial Approval STEVEN BACK
Insulation 12/5/2022 Corrections Issued ALEXANDER HANDY
Interior/Exterior Lathing 12/5/2022 Not Ready for Inspection ALEXANDER HANDY
Drywall Nailing 12/20/2022 Not Ready for Inspection ALEXANDER HANDY
Insulation 12/20/2022 Not Ready for Inspection ALEXANDER HANDY
Drywall Nailing 12/22/2022 Approved JEFFREY BULL
Insulation 12/22/2022 Approved JEFFREY BULL