8506 W TUJUNGA VALLEY ST 91040
Certificate Information: 8506 W TUJUNGA VALLEY ST 91040
- Application / Permit
- 21014-20000-06031
- Plan Check / Job No.
- B21VN16715
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 23'-11" X 19'-3" ADDITION TO THE (E) SFD.
- Permit Issued
- Issued on 3/15/2022
- Issuing Office
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2021 | SERGIO MUNIZ |
| Corrections Issued | 12/11/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 2/17/2022 | SERGIO MUNIZ |
| Plan Check Approved | 3/15/2022 | SERGIO MUNIZ |
| Issued | 3/15/2022 | APPLICANT |
| Building Plans Picked Up | 3/17/2022 | APPLICANT |
| CofO in Progress | 12/21/2022 | WILLIAM WREN |
| CofO Issued | 12/24/2022 | MICHAEL SMITH |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/25/2022 | JOSE DUARTE-DIAZ |
| Watercourse | Cleared | 1/26/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2022 | JOSE DUARTE-DIAZ |
| Grading Pre-Inspection | Cleared | 3/2/2022 | VASIL MIHALEV |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 1819 SUNSHINE COURT GLENDALE, CA 91208 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/24/2022 | Approved | MATTHEW NELSON |
| Wood Frame | 4/11/2022 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/19/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/19/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 4/19/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/25/2022 | Approved | MATTHEW NELSON |
| Insulation | 4/27/2022 | Approved | MATTHEW NELSON |
| Drywall Nailing | 4/29/2022 | Approved | MICHEL ABAJAN |
| Final | 12/14/2022 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 12/14/2022 | Corrections Issued | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 12/14/2022 | SGSOV Approved | WILLIAM WREN |
| Smoke Detectors | 12/14/2022 | Approved | WILLIAM WREN |
| Final | 12/20/2022 | OK to Issue CofO | WILLIAM WREN |
| Green Building Final | 12/20/2022 | Approved | WILLIAM WREN |