20447 W STRATHERN ST 91306
Certificate Information: 20447 W STRATHERN ST 91306
- Application / Permit
- 21014-20000-06018
- Plan Check / Job No.
- B21VN16667
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan ADD 15' X 20' TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 1/18/2022
- Issuing Office
- Current Status
- CofO Issued on 11/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2021 | SELLA BENYAMIN |
| Corrections Issued | 12/7/2021 | SELLA BENYAMIN |
| Plan Check Approved | 1/6/2022 | SELLA BENYAMIN |
| Issued | 1/18/2022 | APPLICANT |
| CofO in Progress | 11/9/2022 | STEVEN BACK |
| Permit Finaled | 11/10/2022 | JOHN JANSON |
| CofO Issued | 11/10/2022 | JOHN JANSON |
| Permit Finaled | 11/10/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/27/2021 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 12/27/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/29/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: NA76761 | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/24/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 2/24/2022 | Partial Approval | STEVEN BACK |
| Sewer | 2/24/2022 | Approved | STEVEN BACK |
| Deputy Drilled-In Anchors | 2/25/2022 | Conditional Approval | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 3/24/2022 | Approved | STEVEN BACK |
| PLUMBING-Rough | 5/4/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 6/8/2022 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 6/8/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2022 | Approved | STEVEN BACK |
| HVAC-Rough | 6/8/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 6/14/2022 | Not Ready for Inspection | STEVEN BACK |
| Green Building Rough | 6/14/2022 | Not Ready for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 6/14/2022 | Not Ready for Inspection | STEVEN BACK |
| Green Building Rough | 6/27/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 6/27/2022 | Partial Approval | STEVEN BACK |
| Shower Pan | 6/27/2022 | Approved | STEVEN BACK |
| Insulation | 7/5/2022 | Corrections Issued | STEVEN BACK |
| Insulation | 7/11/2022 | Approved | STEVEN BACK |
| Drywall Nailing | 7/15/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 7/15/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 10/31/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 10/31/2022 | Approved | STEVEN BACK |
| Final | 10/31/2022 | Corrections Issued | STEVEN BACK |
| HVAC-Final | 10/31/2022 | Approved | STEVEN BACK |
| PLUMBING-Final | 10/31/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 10/31/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 11/9/2022 | Approved | STEVEN BACK |
| Final | 11/9/2022 | OK to Issue CofO | STEVEN BACK |
| HVAC-Final | 11/9/2022 | Approved | STEVEN BACK |
| PLUMBING-Final | 11/9/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/9/2022 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 11/9/2022 | Approved | STEVEN BACK |