16135 W OTSEGO ST 91436

Certificate Information: 16135 W OTSEGO ST 91436

Application / Permit
21014-20000-05988
Plan Check / Job No.
B21VN16576
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EXPAND (E) MASTER BEDROOM & BATHROOM (27' X 23'-6") & ADD PATIO COVER (17' X 12'-8") AT REAR & EXPAND FRONT ENTRY (1'-10" X 5'-11") TO (E) 1-STORY SFD W/ ATTACHED GARAGE; MAJOR REMODEL; REFRAME PORTION OF (E) ROOF (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 8/30/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2021 APPLICANT
Assigned to Plan Check Engineer 12/29/2021 NILOOFAR MEHRAIN
Corrections Issued 1/4/2022 NILOOFAR MEHRAIN
Quality Review Completed 1/7/2022 STEVEN KIM
Building Plans Picked Up 1/7/2022 APPLICANT
Applicant returned to address corrections 2/24/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/22/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 4/20/2022 NILOOFAR MEHRAIN
Plan Check Approved 5/4/2022 NILOOFAR MEHRAIN
Issued 8/30/2022 APPLICANT
CofO in Progress 4/29/2025 JOHN COLEMAN
Permit Finaled 5/1/2025 JOHN JANSON
CofO Issued 5/1/2025 JOHN JANSON
Permit Finaled 5/1/2025 JOHN JANSON

Permit Application Clearance Information

Low Impact Development Cleared 3/16/2022 ANTHONY VARGAS
Eng Process Fee Ord 176,300 Cleared 8/29/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 8/29/2022 MEGAN GODINEZ
Sewer availability Cleared 8/29/2022 MEGAN GODINEZ

Contact Information

Contractor Orange Innovation Inc; Lic. No.: 832810-B 22920 CALIFA ST      WOODLAND HILLS, CA 91367
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/4/2022 Approved VINCENT HANLEY
Insulation 11/18/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 11/18/2022 Partial Approval VINCENT HANLEY
Wood Frame 11/18/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/28/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/5/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/1/2023 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 2/1/2023 Approved VINCENT HANLEY
Green Building Rough 2/1/2023 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 2/1/2023 Approved VINCENT HANLEY
MERV13>=Rough 2/1/2023 Approved VINCENT HANLEY
PLUMBING-Rough 2/1/2023 Approved VINCENT HANLEY
Deputy Wood Construction 2/3/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/9/2023 Not Ready for Inspection SEAN HAUPT
Green Building Rough 2/9/2023 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 2/13/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/13/2023 Approved VINCENT HANLEY
Green Building Rough 2/13/2023 Approved VINCENT HANLEY
Insulation 2/21/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 2/21/2023 Partial Approval JESUS PINEDA
Drywall Nailing 2/27/2023 Approved JESUS PINEDA
Shower Pan 2/27/2023 Corrections Issued JESUS PINEDA
Shower Pan 3/1/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/10/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 12/19/2023 No Access for Inspection VINCENT HANLEY
ELECTRICAL-Final 6/26/2024 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 6/26/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 6/26/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 3/26/2025 Corrections Issued THOMAS FINNILA
HVAC-Final 3/26/2025 Corrections Issued THOMAS FINNILA
PLUMBING-Final 3/26/2025 Corrections Issued THOMAS FINNILA
ELECTRICAL-Final 4/2/2025 Approved JOHN COLEMAN
Final 4/2/2025 Partial Inspection JOHN COLEMAN
Green Building Final 4/2/2025 Approved JOHN COLEMAN
HVAC-Final 4/2/2025 Approved JOHN COLEMAN
MERV13>=Final 4/2/2025 Approved JOHN COLEMAN
PLUMBING-Final 4/2/2025 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 4/2/2025 SGSOV Approved JOHN COLEMAN
Smoke Detectors 4/2/2025 Approved JOHN COLEMAN
Special/Order Compliance 4/9/2025 Corrections Issued JOHN COLEMAN
Final 4/29/2025 OK to Issue CofO JOHN COLEMAN