6515 N WHITE OAK AVE 91335
Certificate Information: 6515 N WHITE OAK AVE 91335
- Application / Permit
- 21014-20000-05985
- Plan Check / Job No.
- B21VN16562
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 25' X 18'-6" ADDITION TO AND CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d).
- Permit Issued
- Issued on 2/3/2022
- Issuing Office
- Current Status
- CofO Issued on 1/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2021 | SERGIO MUNIZ |
| Corrections Issued | 12/6/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 12/28/2021 | SERGIO MUNIZ |
| Plan Check Approved | 1/19/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 1/19/2022 | APPLICANT |
| Issued | 2/3/2022 | APPLICANT |
| CofO in Progress | 1/2/2024 | JEFFREY BULL |
| CofO Issued | 1/19/2024 | JOHN JANSON |
| Permit Finaled | 1/19/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/9/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/9/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/29/2022 | Conditional Approval | MORRIS JACKSON |
| PLUMBING-Rough | 4/25/2022 | Partial Approval | VINCENT HANLEY |
| Sewer | 4/25/2022 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 5/4/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2022 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 9/2/2022 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 9/2/2022 | Approved | JEFFREY BULL |
| Green Building Rough | 9/2/2022 | Approved | JEFFREY BULL |
| HVAC-Rough | 9/2/2022 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 9/2/2022 | Approved | JEFFREY BULL |
| Insulation | 9/19/2022 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 9/19/2022 | Partial Approval | JEFFREY BULL |
| Shower Pan | 9/19/2022 | Approved | JEFFREY BULL |
| Drywall Nailing | 9/29/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/29/2022 | Approved | JUSTIN HAWLEY |
| Final | 10/16/2023 | Corrections Issued | JEFFREY BULL |
| PLUMBING-Final | 10/16/2023 | Approved | JEFFREY BULL |
| Pre-Inspection | 12/7/2023 | Approved | JEFFREY BULL |
| Final | 12/21/2023 | Corrections Issued | JEFFREY BULL |
| Service/Power Release | 12/21/2023 | Approved | JEFFREY BULL |
| Final | 12/27/2023 | Not Ready for Inspection | JEFFREY BULL |
| Footing/Foundation/Slab | 12/27/2023 | Approved | JEFFREY BULL |
| Green Building Final | 12/27/2023 | Not Ready for Inspection | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 12/27/2023 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 12/27/2023 | Approved | JEFFREY BULL |
| Final | 1/3/2024 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 1/3/2024 | Approved | JEFFREY BULL |