7707 N LOUISE AVE 91325
Certificate Information: 7707 N LOUISE AVE 91325
- Application / Permit
- 21014-20000-05981
- Plan Check / Job No.
- B21VN16553
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Add irr. 23'-3" x 16'-9" master bedroom to the existing single-family dwelling per engineer
- Permit Issued
- Issued on 12/22/2021
- Issuing Office
- Current Status
- CofO Issued on 8/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2021 | ANGELICA DAVE |
| Corrections Issued | 12/1/2021 | ANGELICA DAVE |
| Applicant returned to address corrections | 12/15/2021 | ANGELICA DAVE |
| Issued | 12/22/2021 | APPLICANT |
| Building Plans Picked Up | 12/22/2021 | APPLICANT |
| CofO in Progress | 8/2/2022 | JAVIER RAMOS JR |
| CofO Issued | 8/11/2022 | MICHAEL SMITH |
| Permit Finaled | 8/11/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2021 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 12/2/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/2/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan, Souren Krist; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/18/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 1/21/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 1/21/2022 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2022 | Approved | RAUL OLAGI |
| Sewer | 2/15/2022 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 3/7/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 3/7/2022 | Corrections Issued | ALAN MORELOS |
| Sewer | 3/7/2022 | Approved | ALAN MORELOS |
| Insulation | 3/10/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 3/10/2022 | Partial Approval | ALAN MORELOS |
| PLUMBING-Rough | 3/10/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 3/15/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 3/15/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 3/15/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 3/23/2022 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 4/1/2022 | SGSOV Not Ready | RAUL OLAGI |
| Final | 4/7/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 4/7/2022 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 4/7/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 4/7/2022 | Corrections Issued | RAUL OLAGI |
| Final | 6/2/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 6/2/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 6/2/2022 | Approved | JAVIER RAMOS JR |
| Final | 6/23/2022 | Not Ready for Inspection | ALAN MORELOS |
| Green Building Final | 6/23/2022 | Approved | ALAN MORELOS |
| Final | 8/2/2022 | OK to Issue CofO | JAVIER RAMOS JR |