7707 N LOUISE AVE 91325

Certificate Information: 7707 N LOUISE AVE 91325

Application / Permit
21014-20000-05981
Plan Check / Job No.
B21VN16553
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Add irr. 23'-3" x 16'-9" master bedroom to the existing single-family dwelling per engineer
Permit Issued
Issued on 12/22/2021
Issuing Office
Current Status
CofO Issued on 8/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2021 APPLICANT
Assigned to Plan Check Engineer 12/1/2021 ANGELICA DAVE
Corrections Issued 12/1/2021 ANGELICA DAVE
Applicant returned to address corrections 12/15/2021 ANGELICA DAVE
Issued 12/22/2021 APPLICANT
Building Plans Picked Up 12/22/2021 APPLICANT
CofO in Progress 8/2/2022 JAVIER RAMOS JR
CofO Issued 8/11/2022 MICHAEL SMITH
Permit Finaled 8/11/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/2/2021 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 12/2/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 12/2/2021 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan, Souren Krist; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/18/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 1/21/2022 Approved RAUL OLAGI
PLUMBING-Rough 1/21/2022 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/15/2022 Approved RAUL OLAGI
Sewer 2/15/2022 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Rough 3/7/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 3/7/2022 Corrections Issued ALAN MORELOS
Sewer 3/7/2022 Approved ALAN MORELOS
Insulation 3/10/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 3/10/2022 Partial Approval ALAN MORELOS
PLUMBING-Rough 3/10/2022 Approved ALAN MORELOS
BUILDING-Rough-Frame 3/15/2022 Approved RAUL OLAGI
Drywall Nailing 3/15/2022 Approved RAUL OLAGI
Green Building Rough 3/15/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 3/23/2022 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 4/1/2022 SGSOV Not Ready RAUL OLAGI
Final 4/7/2022 Corrections Issued RAUL OLAGI
Green Building Final 4/7/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 4/7/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 4/7/2022 Corrections Issued RAUL OLAGI
Final 6/2/2022 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 6/2/2022 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 6/2/2022 Approved JAVIER RAMOS JR
Final 6/23/2022 Not Ready for Inspection ALAN MORELOS
Green Building Final 6/23/2022 Approved ALAN MORELOS
Final 8/2/2022 OK to Issue CofO JAVIER RAMOS JR