10804 N MCVINE AVE 91040
Certificate Information: 10804 N MCVINE AVE 91040
- Application / Permit
- 21014-20000-05968
- Plan Check / Job No.
- B21VN16479
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 12' X 24'-9" ADDITION TO (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/8/2022
- Issuing Office
- Current Status
- CofO Issued on 5/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2021 | RAPHAEL ROSAS |
| Corrections Issued | 1/1/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/16/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 3/27/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 3/29/2022 | APPLICANT |
| Issued | 4/8/2022 | APPLICANT |
| CofO in Progress | 5/1/2023 | WILLIAM WREN |
| CofO Issued | 5/2/2023 | MICHAEL SMITH |
| Permit Finaled | 5/2/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 1/14/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 1/14/2022 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 3/7/2022 | MANUEL TEJADA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazarians,, Harmick Edward; Lic. No.: C91232 | 9825 OSO AVE CHATSWORTH, CA 91311 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/25/2022 | Corrections Issued | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 5/11/2022 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 5/12/2022 | Approved | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 5/20/2022 | Approved | MATTHEW NELSON |
| Deputy Wood Construction | 7/11/2022 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 7/18/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 7/18/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 7/21/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Rough-Elec/Plmb/HVAC | 7/21/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 7/28/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/28/2022 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 7/28/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 7/28/2022 | Approved | MATTHEW NELSON |
| Insulation | 8/12/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/12/2022 | Approved | MATTHEW NELSON |
| Drywall Nailing | 8/26/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/26/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 4/14/2023 | Not Ready for Inspection | WILLIAM WREN |
| Final | 4/14/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 4/14/2023 | Approved | WILLIAM WREN |
| HVAC-Final | 4/14/2023 | Approved | WILLIAM WREN |
| PLUMBING-Final | 4/14/2023 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 4/14/2023 | SGSOV Approved | WILLIAM WREN |
| Smoke Detectors | 4/14/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 4/28/2023 | Approved | WILLIAM WREN |
| Final | 4/28/2023 | OK to Issue CofO | WILLIAM WREN |