11939 1/2 W VALERIO ST 91605

Certificate Information: 11939 1/2 W VALERIO ST 91605

Application / Permit
21014-20000-05967
Plan Check / Job No.
B21VN16478
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
253 SQ. FT. ADDITION TO AND CONVERT THE (E) 400 SQ. FT. DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). PER WFPP.
Permit Issued
Issued on 5/6/2022
Issuing Office
Current Status
CofO Issued on 4/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2021 APPLICANT
Assigned to Plan Check Engineer 12/3/2021 JESSE ARELLANO
Corrections Issued 12/4/2021 JESSE ARELLANO
Applicant returned to address corrections 1/20/2022 ZAW HAN
Applicant returned to address corrections 2/23/2022 JESSE ARELLANO
Applicant returned to address corrections 4/6/2022 JESSE ARELLANO
Applicant returned to address corrections 4/28/2022 JESSE ARELLANO
Plan Check Approved 5/2/2022 JESSE ARELLANO
Building Plans Picked Up 5/2/2022 APPLICANT
Issued 5/6/2022 APPLICANT
CofO in Progress 1/7/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 4/3/2025 RUBEN SALAS
CofO Issued 4/3/2025 RUBEN SALAS
Permit Finaled 4/3/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/10/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/10/2021 CARLOS AGUILERA
Sewer availability Cleared 12/10/2021 CARLOS AGUILERA
Green Code Cleared 2/25/2022 JESSE ARELLANO
Roof/Waste drainage to street Cleared 2/26/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/27/2024 Approved JOHN HAYES
Excavation/Setback/Form/Re-Bar 3/6/2024 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 3/18/2024 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 3/27/2024 Corrections Issued JOHN HAYES
Green Building Rough 3/27/2024 Not Ready for Inspection JOHN HAYES
METHANE-Rough 3/27/2024 Approved JOHN HAYES
BUILDING-Rough-Frame 5/7/2024 Corrections Issued JOHN HAYES
Green Building Rough 5/7/2024 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 5/7/2024 Approved JOHN HAYES
Deputy Wood Construction 6/13/2024 Conditional Approval JUAN VALENZUELA
Insulation 6/20/2024 Approved JOSE AVILA
Drywall Nailing 7/1/2024 Approved JOSE AVILA
Interior/Exterior Lathing 7/15/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 7/15/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Underground Mechanical 7/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 7/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 7/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Underground Mechanical 9/5/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 10/15/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 10/15/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 10/15/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Green Building Final 10/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 10/15/2024 Approved ROBERTO PALACIOS-LOPEZ
METHANE-Barrier 10/15/2024 Approved ROBERTO PALACIOS-LOPEZ
METHANE-Subgrade 10/15/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 10/15/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 10/15/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 10/16/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 10/16/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 10/16/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 10/16/2024 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 10/16/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 11/14/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 11/14/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 11/14/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 11/14/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 11/14/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 12/30/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 12/30/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 12/30/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 12/31/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 12/31/2024 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 12/31/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 1/6/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 1/6/2025 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 1/6/2025 Approved ROBERTO PALACIOS-LOPEZ