11939-11941 W VALERIO ST 91605
Certificate Information: 11939-11941 W VALERIO ST 91605
- Application / Permit
- 21014-20000-05966
- Plan Check / Job No.
- B21VN16477
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 14'6" X 19'6" (193 SQ. FT.) ADDITION, AND A 3' X 5' (15 SQ. FT.) PATIO COVER ADDED TO THE 9E) SFD. INTERIOR REMODEL TO CONVERT THE (E) UNIT INTO A THREE BEDROOM, TWO BATHROOM, WITH LAUNDRY, KITCHEN, DINING AND LIVING ROOM AT 11939 W VALERIO ST (DUPLEX)
- Permit Issued
- Issued on 3/21/2022
- Issuing Office
- Current Status
- CofO Issued on 4/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2021 | JESSE ARELLANO |
| Corrections Issued | 11/30/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 2/17/2022 | JESSE ARELLANO |
| Plan Check Approved | 3/9/2022 | JESSE ARELLANO |
| Building Plans Picked Up | 3/10/2022 | APPLICANT |
| Issued | 3/21/2022 | APPLICANT |
| CofO in Progress | 2/2/2024 | JOHN HAYES |
| Permit Finaled | 4/2/2024 | RUBEN SALAS |
| CofO Issued | 4/2/2024 | RUBEN SALAS |
| Permit Finaled | 4/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/26/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/26/2022 | CARLOS AGUILERA |
| Green Code | Cleared | 2/17/2022 | JESSE ARELLANO |
| Tenant Habitability Plan | Cleared | 2/28/2022 | MICHAEL SOTO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/22/2023 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 8/22/2023 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 8/29/2023 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 8/29/2023 | Corrections Issued | JOHN HAYES |
| METHANE-Barrier | 8/29/2023 | Not Ready for Inspection | JOHN HAYES |
| METHANE-Subgrade | 8/29/2023 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 9/5/2023 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 9/5/2023 | Approved | JOHN HAYES |
| METHANE-Barrier | 9/5/2023 | Approved | JOHN HAYES |
| METHANE-Subgrade | 9/5/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 11/14/2023 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 1/8/2024 | Approved | JOHN HAYES |
| Final | 1/8/2024 | Corrections Issued | JOHN HAYES |
| Green Building Final | 1/8/2024 | Approved | JOHN HAYES |
| Green Building Rough | 1/8/2024 | Approved | JOHN HAYES |
| METHANE-Final | 1/8/2024 | Approved | JOHN HAYES |
| METHANE-Rough | 1/8/2024 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/8/2024 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 1/8/2024 | Approved | JOHN HAYES |
| Final | 2/2/2024 | OK to Issue CofO | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/2/2024 | SGSOV Approved | JOHN HAYES |