5131 N LEDGE AVE 91601

Certificate Information: 5131 N LEDGE AVE 91601

Application / Permit
21014-20000-05960
Plan Check / Job No.
B21VN16464
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF A 6' x 9.5' (54 SQ. FT.) BATHROOM AND AN IRREGULAR 17'10" x 25'10" (440 SQ. FT.) COVERED PATIO.
Permit Issued
Issued on 6/3/2022
Issuing Office
Current Status
CofO Issued on 4/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2021 APPLICANT
Assigned to Plan Check Engineer 12/6/2021 LUIS RINCON
Corrections Issued 12/6/2021 LUIS RINCON
Plan Check Approved 5/3/2022 LUIS RINCON
Building Plans Picked Up 5/23/2022 APPLICANT
Issued 6/3/2022 APPLICANT
CofO in Progress 3/28/2023 JOHN HAYES
Permit Finaled 4/6/2023 MICHAEL SMITH
CofO Issued 4/6/2023 MICHAEL SMITH
Permit Finaled 4/6/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/10/2022 CARLOS AGUILERA
Low Impact Development Cleared 4/18/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 4/21/2022 CARLOS AGUILERA

Contact Information

Architect Himes,, John A; Lic. No.: C25478 17155 LISETTE STREET      GRANADA HILLS, CA 91344
Contractor Plaskoff Matt Construction Inc; Lic. No.: 660059-B 6827 VALJEAN AVE      VAN NUYS, CA 91406

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/20/2022 Partial Approval JOHN HAYES
Deputy Reinf. Concrete 7/25/2022 Conditional Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 8/1/2022 Approved CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 8/24/2022 Partial Approval JOHN HAYES
PLUMBING-Rough 8/24/2022 Approved JOHN HAYES
BUILDING-Rough-Frame 8/29/2022 Partial Approval JOHN HAYES
ELECTRICAL-Rough 8/29/2022 Partial Approval JOHN HAYES
HVAC-Rough 8/29/2022 Partial Approval JOHN HAYES
PLUMBING-Rough 8/29/2022 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 9/1/2022 Partial Approval ALAN MORELOS
Insulation 9/1/2022 Approved ALAN MORELOS
Drywall Nailing 9/20/2022 Approved CALEB MEISTER
Drywall Nailing 9/20/2022 Approved JOHN HAYES
ELECTRICAL-Rough 9/20/2022 Approved JOHN HAYES
Interior/Exterior Lathing 9/26/2022 Partial Approval JOHN HAYES
Shower Pan 10/13/2022 Approved ALAN MORELOS
BUILDING-Rough-Frame 3/10/2023 Approved JOHN HAYES
Final 3/10/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 3/10/2023 Approved JOHN HAYES
Green Building Final 3/10/2023 Approved JOHN HAYES
Green Building Rough 3/10/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 3/10/2023 SGSOV Approved JOHN HAYES
Smoke Detectors 3/10/2023 Approved JOHN HAYES
Final 3/28/2023 OK to Issue CofO JOHN HAYES