10873 N ENCINO AVE 91344

Certificate Information: 10873 N ENCINO AVE 91344

Application / Permit
21014-20000-05955
Plan Check / Job No.
B21VN16453
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, 20'-6" X 33'-0" SECOND FLOOR ADDITION TO (E) SFD.
Permit Issued
Issued on 6/14/2022
Issuing Office
Current Status
CofO Issued on 7/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2021 APPLICANT
Assigned to Plan Check Engineer 12/29/2021 ARTIN ZARUKIAN
Corrections Issued 1/3/2022 ARTIN ZARUKIAN
Quality Review Completed 1/7/2022 STEVEN KIM
Plan Check Approved 5/18/2022 ARTIN ZARUKIAN
Building Plans Picked Up 5/19/2022 APPLICANT
Issued 6/14/2022 APPLICANT
CofO in Progress 7/26/2023 STEVEN BACK
CofO Issued 7/31/2023 JOHN JANSON
Permit Finaled 7/31/2023 JOHN JANSON

Permit Application Clearance Information

Miscellaneous Cleared 1/14/2022 NELSON RODRIGUEZ
Low Impact Development Cleared 4/4/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 4/4/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 4/7/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 4/7/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/24/2022 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 10/24/2022 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 10/24/2022 Not Ready for Inspection SEAN HAUPT
Pre-Inspection 10/24/2022 Not Ready for Inspection SEAN HAUPT
Excavation/Setback/Form/Re-Bar 11/1/2022 Approved JEFFREY PARD
PLUMBING-Rough 11/1/2022 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 11/16/2022 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 11/16/2022 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Partial Approval DAVID SCANTLIN
Special/Order Compliance 11/21/2022 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 11/30/2022 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 12/9/2022 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 12/19/2022 Approved STEVEN BACK
Interior/Exterior Lathing 12/28/2022 Partial Approval STEVEN BACK
Rough-Elec/Plmb/HVAC 1/31/2023 Approved STEVEN BACK
BUILDING-Rough-Frame 2/2/2023 Approved STEVEN BACK
Green Building Rough 2/2/2023 Approved STEVEN BACK
Insulation 2/15/2023 Approved JUSTIN HAWLEY
Drywall Nailing 3/10/2023 Approved JOHN KIDWELL
Shower Pan 3/10/2023 Approved JOHN KIDWELL
Drywall Nailing 3/14/2023 Approved STEVEN BACK
Interior/Exterior Lathing 3/14/2023 Approved STEVEN BACK
ELECTRICAL-Final 7/6/2023 Corrections Issued HENRY KIM
Final 7/6/2023 Corrections Issued HENRY KIM
Footing/Foundation/Slab 7/6/2023 Approved HENRY KIM
Green Building Final 7/6/2023 Approved HENRY KIM
HVAC-Final 7/6/2023 Corrections Issued HENRY KIM
PLUMBING-Final 7/6/2023 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 7/6/2023 SGSOV Not Ready HENRY KIM
Smoke Detectors 7/6/2023 Approved HENRY KIM
ELECTRICAL-Final 7/26/2023 Approved STEVEN BACK
Final 7/26/2023 OK to Issue CofO STEVEN BACK
HVAC-Final 7/26/2023 Approved STEVEN BACK
PLUMBING-Final 7/26/2023 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 7/26/2023 SGSOV Approved STEVEN BACK