10578 W BRADBURY ROAD 90064

Certificate Information: 10578 W BRADBURY ROAD 90064

Application / Permit
21014-20000-05941
Plan Check / Job No.
B21VN16436
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR INT. REMODEL AND 1ST AND 2ND STORY ADDITION AND GARAGE ADDITION TO (E) SFD FIRE SPRINKLER NFPA 13D
Permit Issued
Issued on 4/22/2022
Issuing Office
Current Status
CofO Issued on 7/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2021 APPLICANT
Assigned to Plan Check Engineer 12/9/2021 MOHAMMAD ESMAILI
Corrections Issued 12/11/2021 MOHAMMAD ESMAILI
Quality Review Completed 12/14/2021 OMID HEDAYAT
Building Plans Picked Up 12/21/2021 APPLICANT
Plan Check Approved 3/25/2022 MOHAMMAD ESMAILI
Issued 4/22/2022 APPLICANT
Permit Finaled 7/31/2024 DANIEL ORRANTE
CofO Issued 7/31/2024 DANIEL ORRANTE
Permit Finaled 7/31/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/8/2022 ANDREW SLUSSER
Permit Cleared 1/8/2022 ANDREW SLUSSER
Sewer availability Cleared 1/8/2022 ANDREW SLUSSER
Specific Plan Cleared 1/19/2022 DYLAN SITTIG
ZI Cleared 1/19/2022 DYLAN SITTIG
Low Impact Development Cleared 2/28/2022 MARCO SANCHEZ
Trees in Parkway Cleared 3/4/2022 ADALBERTO VERA
Roof/Waste drainage to street Cleared 3/7/2022 JOSE HERNANDEZ
Specific Plan Cleared 3/14/2022 VALERIA CEJA
GPI Written Notices Cleared 3/25/2022 MOHAMMAD ESMAILI
Grading Pre-Inspection Cleared 3/25/2022 MOHAMMAD ESMAILI

Contact Information

Contractor Kempler & Company Incorporated; Lic. No.: 562533-B 14731 SUTTON STREET      SHERMAN OAKS, CA 91403

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 6/22/2022 Conditional Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 6/27/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 6/27/2022 Partial Approval KEVIN SARGSYAN
Pre-Inspection 6/27/2022 Partial Approval KEVIN SARGSYAN
Deputy Wood Construction 7/6/2022 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 7/7/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 7/7/2022 Partial Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 7/8/2022 Partial Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 7/14/2022 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 7/14/2022 Approved KEVIN SARGSYAN
Deputy Steel/Welding 7/20/2022 No Result Entered RONALD WEBER
Floor/Roof Diaphrgm/Shear Wall 7/25/2022 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 7/27/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 7/28/2022 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 8/22/2022 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/22/2022 Partial Approval JOHN KIDWELL
Deputy Wood Construction 10/14/2022 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 12/6/2022 Approved ASHLEY THOMPSON
HVAC-Rough 12/6/2022 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 12/13/2022 Approved OGANES TARAKHCHYAN
Deputy Wood Construction 2/6/2023 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 2/23/2023 Approved EVAN COOPER
Green Building Rough 2/23/2023 Approved EVAN COOPER
Interior/Exterior Lathing 2/23/2023 Partial Approval EVAN COOPER
Shower Pan 2/23/2023 Approved EVAN COOPER
Verify Sprinkler Sign Off 2/23/2023 Approved EVAN COOPER
Insulation 3/2/2023 Approved CLAYTON GRAHAM
Drywall Nailing 3/20/2023 Approved ASHLEY THOMPSON
ELECTRICAL-Final 5/29/2024 Corrections Issued ASHLEY THOMPSON
Final 5/29/2024 Corrections Issued ASHLEY THOMPSON
Green Building Final 5/29/2024 Corrections Issued ASHLEY THOMPSON
HVAC-Final 5/29/2024 Approved ASHLEY THOMPSON
PLUMBING-Final 5/29/2024 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 5/29/2024 SGSOV Approved ASHLEY THOMPSON
Smoke Detectors 5/29/2024 Approved ASHLEY THOMPSON
ELECTRICAL-Final 6/5/2024 Approved TEMISTOCLES CAAL
Final 7/26/2024 Conditional Approval ASHLEY THOMPSON
Green Building Final 7/26/2024 Approved ASHLEY THOMPSON