10135 W SULLY DR 91352

Certificate Information: 10135 W SULLY DR 91352

Application / Permit
21014-20000-05939
Plan Check / Job No.
B21VN16435
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL & 2ND STORY ADDITION TO (E) SINGLE FAMILY DWELLING WITH COVERED PATIO AND DECK. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/24/2022
Issuing Office
Metro
Current Status
CofO Issued on 6/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 COLIN LOREDO
Corrections Issued 1/18/2022 COLIN LOREDO
Quality Review Completed 1/20/2022 OMID HEDAYAT
Building Plans Picked Up 1/21/2022 APPLICANT
Applicant returned to address corrections 4/22/2022 COLIN LOREDO
Plan Check Approved 6/17/2022 COLIN LOREDO
Issued 6/24/2022 APPLICANT
CofO in Progress 5/21/2024 DAVID ANDERSON
Permit Finaled 6/26/2024 RUBEN SALAS
CofO Issued 6/26/2024 RUBEN SALAS
Permit Finaled 6/26/2024 RUBEN SALAS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/1/2022 JOSE DUARTE-DIAZ
BHO/Hillside ordinance Cleared 2/1/2022 JOSE DUARTE-DIAZ
BHO/Hillside ordinance Cleared 2/1/2022 JOSE DUARTE-DIAZ
BHO/Hillside ordinance Cleared 2/1/2022 JOSE DUARTE-DIAZ
BHO/Hillside ordinance Cleared 2/1/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 2/8/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 2/8/2022 JOSE DUARTE-DIAZ
Hydrant and Access approval Cleared 3/5/2022 CINDY JOSSELYN
ZA Case Cleared 3/14/2022 ANACANY HURTADO
Low Impact Development Cleared 5/12/2022 NICK RAYGOZA
Roof/Waste drainage to street Cleared 6/7/2022 JOSE DUARTE-DIAZ
GPI Written Notices Cleared 6/17/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 6/17/2022 COLIN LOREDO

Contact Information

Contractor Simply Done Inc; Lic. No.: 936059-B 6540 HAYVENHURST AVE UNIT 10      LAKE BALBOA, CA 91406
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/7/2022 Approved DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 10/19/2022 Approved DAVID ANDERSON
Footing/Foundation/Slab 10/19/2022 Approved DAVID ANDERSON
Deputy Steel/Welding 11/30/2022 Conditional Approval DAVID MATSON
PLUMBING-Rough 12/1/2022 Partial Approval MATTHEW NELSON
Underground Mechanical 12/1/2022 Not Ready for Inspection MATTHEW NELSON
Wood Frame 12/12/2022 Approved DAVID ANDERSON
Underground Mechanical 12/14/2022 No Access for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 12/19/2022 Partial Approval DAVID ANDERSON
Insulation 12/19/2022 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 1/6/2023 Approved DAVID ANDERSON
Deputy Wood Construction 4/11/2023 Conditional Approval MICHAEL SMITH
Floor/Roof Diaphrgm/Shear Wall 4/11/2023 Approved DAVID ANDERSON
HVAC-Rough 4/11/2023 Approved DAVID ANDERSON
PLUMBING-Rough 4/11/2023 Approved DAVID ANDERSON
ELECTRICAL-Rough 5/16/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 6/5/2023 Corrections Issued DAVID ANDERSON
Green Building Rough 6/5/2023 Corrections Issued DAVID ANDERSON
MERV13>=Rough 6/5/2023 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 6/5/2023 Not Ready for Inspection DAVID ANDERSON
Wood Frame 6/5/2023 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 6/15/2023 Approved DAVID ANDERSON
Green Building Rough 6/15/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 6/15/2023 Approved DAVID ANDERSON
Special/Order Compliance 6/15/2023 Corrections Issued DAVID ANDERSON
Verify Sprinkler Sign Off 6/15/2023 Approved DAVID ANDERSON
Insulation 6/27/2023 Approved DAVID ANDERSON
Drywall Nailing 7/13/2023 Partial Approval DAVID ANDERSON
Interior/Exterior Lathing 9/5/2023 Approved DAVID ANDERSON
Shower Pan 9/5/2023 Approved DAVID ANDERSON
Drywall Nailing 10/10/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 10/10/2023 Approved DAVID ANDERSON
ELECTRICAL-Final 4/26/2024 Corrections Issued DAVID ANDERSON
HVAC-Final 4/26/2024 Approved DAVID ANDERSON
PLUMBING-Final 4/26/2024 Approved DAVID ANDERSON
Final 5/20/2024 OK to Issue CofO DAVID ANDERSON
Green Building Final 5/20/2024 Approved DAVID ANDERSON
MERV13>=Final 5/20/2024 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 5/20/2024 SGSOV Approved DAVID ANDERSON
Smoke Detectors 5/20/2024 Approved DAVID ANDERSON