13816 W CANTLAY ST 91405
Certificate Information: 13816 W CANTLAY ST 91405
- Application / Permit
- 21014-20000-05928
- Plan Check / Job No.
- B21VN16402
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- 19'-1" X 19'-1" (345 SF) PATIO ADDITION TO EXISTING SFD W JADU
- Permit Issued
- Issued on 6/9/2022
- Issuing Office
- Current Status
- CofO Issued on 11/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2022 | STARR CHEN |
| Corrections Issued | 1/6/2022 | STARR CHEN |
| Plan Check Approved | 6/8/2022 | YAQUB MIRZA |
| Issued | 6/9/2022 | APPLICANT |
| Building Plans Picked Up | 6/9/2022 | APPLICANT |
| CofO in Progress | 11/12/2022 | GREGG CUMMINGS |
| CofO Issued | 11/21/2022 | MICHAEL SMITH |
| Permit Finaled | 11/21/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/21/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/7/2022 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 7/15/2022 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 7/20/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/20/2022 | Approved | GREGG CUMMINGS |
| Wood Frame | 7/27/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 8/1/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 8/16/2022 | Partial Approval | GREGG CUMMINGS |
| Drywall Nailing | 9/30/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/10/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 11/10/2022 | Approved | GREGG CUMMINGS |
| Final | 11/10/2022 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 11/10/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 11/10/2022 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 11/10/2022 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 11/10/2022 | Approved | GREGG CUMMINGS |