24215 S STERLING RANCH ROAD 91304
Certificate Information: 24215 S STERLING RANCH ROAD 91304
- Application / Permit
- 21014-20000-05914
- Plan Check / Job No.
- B21VN16365
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 12' X 48' LATTICE ROOF PATIO COVER. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/20/2022
- Issuing Office
- Current Status
- CofO Issued on 9/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2021 | RAPHAEL ROSAS |
| Corrections Issued | 12/4/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/7/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 4/16/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 5/15/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 5/17/2022 | APPLICANT |
| Issued | 5/20/2022 | APPLICANT |
| CofO in Progress | 9/27/2022 | JUSTIN HAWLEY |
| CofO Issued | 9/28/2022 | JOHN JANSON |
| Permit Finaled | 9/28/2022 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2022 | JOSE DUARTE-DIAZ |
| Tract Map conditions | Cleared | 3/2/2022 | MIGUEL GAMBOA |
| Watercourse | Cleared | 3/2/2022 | JOSE DUARTE-DIAZ |
| ZA Case | Cleared | 3/2/2022 | MIGUEL GAMBOA |
| GPI Written Notices | Cleared | 5/15/2022 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 5/15/2022 | RAPHAEL ROSAS |
Contact Information
| Contractor | Alum Works Inc; Lic. No.: 857189-B | 16350 VENTURA BLVD #D103 ENCINO, CA 91436 |
| Engineer | Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 | 1171 JUSTIN AVE APT 3 GLENDALE, CA 91201 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/7/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 8/30/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 8/30/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 8/30/2022 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 8/30/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 9/26/2022 | OK to Issue CofO | JUSTIN HAWLEY |