7637 N RADFORD AVE 91605
Certificate Information: 7637 N RADFORD AVE 91605
- Application / Permit
- 21014-20000-05910
- Plan Check / Job No.
- B21VN16338
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 21' 6" X 25' 6" IRR.-SHAPED BEDROOM/BATHROOM ADDITION TO (E) SFD. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 3/5/2022
- Issuing Office
- Current Status
- CofO Issued on 4/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2022 | RAPHAEL ROSAS |
| Corrections Issued | 1/22/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 2/18/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 2/23/2022 | APPLICANT |
| Issued | 3/5/2022 | APPLICANT |
| CofO in Progress | 3/24/2023 | MATTHEW NELSON |
| CofO Issued | 4/11/2023 | MICHAEL SMITH |
| Permit Finaled | 4/11/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/3/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/7/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 1819 SUNSHINE COURT GLENDALE, CA 91208 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 4/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 4/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 4/28/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/5/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/5/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 6/15/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 6/15/2022 | No Result Entered | ADRIAN GAUTHIER |
| ELECTRICAL-Rough | 6/15/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 6/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 6/15/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/21/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 8/1/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 8/15/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 8/18/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 8/18/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 8/18/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 8/18/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 8/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 8/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 8/31/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 10/17/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 3/23/2023 | Approved | MATTHEW NELSON |
| Final | 3/23/2023 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 3/23/2023 | Approved | MATTHEW NELSON |
| Green Building Rough | 3/23/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 3/23/2023 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 3/23/2023 | Approved | MATTHEW NELSON |