128 S KENTER AVE 90049

Certificate Information: 128 S KENTER AVE 90049

Application / Permit
21014-20000-05890
Plan Check / Job No.
B21VN16233
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2ND STORY ADDITION (20' x 20') TO (E) DET. GARAGE TO CREATE AN ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)-(d) AND ADD NEW 1/2 BATHROOM AT 1ST FLOOR AND NEW COVERED LANDING AT 1ST FLOOR
Permit Issued
Issued on 9/28/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/23/2021 APPLICANT
Assigned to Plan Check Engineer 12/23/2021 COLIN LOREDO
Corrections Issued 12/28/2021 COLIN LOREDO
Quality Review Completed 1/3/2022 OMID HEDAYAT
Building Plans Picked Up 1/5/2022 APPLICANT
Plan Check Approved 3/9/2023 SEAN SHAHMIRI
Issued 9/28/2023 APPLICANT
CofO in Progress 2/7/2025 JESUS RODRIGUEZ
CofO Issued 2/12/2025 RICHARD STEINBACH
Permit Finaled 2/12/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 1/14/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/19/2022 DINAH GARIN
Sewer availability Cleared 1/19/2022 DINAH GARIN
Roof/Waste drainage to street Cleared 2/10/2022 DINAH GARIN
Construction within easement Cleared 2/23/2022 RIDWAN HARDY
Grading Pre-Inspection Cleared 3/9/2023 COLIN LOREDO

Contact Information

Contractor Stout Design Build Inc; Lic. No.: 980007-B 12405 VENICE BLVD 352      LOS ANGELES, CA 90066

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/1/2023 Partial Inspection STEPHANIE SWANSON
Footing/Foundation/Slab 12/1/2023 Partial Inspection STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 12/18/2023 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 1/12/2024 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/16/2024 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 1/18/2024 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 1/23/2024 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 3/12/2024 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 3/12/2024 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 3/12/2024 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 3/22/2024 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 3/22/2024 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/29/2024 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 4/10/2024 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 4/10/2024 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 4/10/2024 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 4/17/2024 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 4/25/2024 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 5/2/2024 Corrections Issued KEVIN SARGSYAN
Green Building Rough 5/2/2024 Approved KEVIN SARGSYAN
HVAC-Rough 5/2/2024 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 5/8/2024 Approved CARLOS MATAMOROS
Green Building Rough 5/8/2024 Approved CARLOS MATAMOROS
HVAC-Rough 5/8/2024 Approved CARLOS MATAMOROS
Insulation 5/24/2024 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Approved ARAM AVEDISIAN
Drywall Nailing 6/14/2024 Approved ARAM AVEDISIAN
Grounding or Bonding 6/24/2024 Not Ready for Inspection ARAM AVEDISIAN
Interior/Exterior Lathing 7/29/2024 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 11/20/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 11/20/2024 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 11/22/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 11/22/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 12/4/2024 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 12/11/2024 Approved JESUS RODRIGUEZ
PLUMBING-Final 12/11/2024 Approved JESUS RODRIGUEZ
Final 1/23/2025 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 1/23/2025 Approved JESUS RODRIGUEZ
Grading Pre-Inspection 1/23/2025 Not Ready for Inspection JESUS RODRIGUEZ
Green Building Final 1/23/2025 Approved JESUS RODRIGUEZ
HVAC-Final 1/23/2025 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 1/23/2025 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 1/23/2025 Approved JESUS RODRIGUEZ
Final 2/3/2025 OK to Issue CofO JESUS RODRIGUEZ