128 S KENTER AVE 90049
Certificate Information: 128 S KENTER AVE 90049
- Application / Permit
- 21014-20000-05890
- Plan Check / Job No.
- B21VN16233
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2ND STORY ADDITION (20' x 20') TO (E) DET. GARAGE TO CREATE AN ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)-(d) AND ADD NEW 1/2 BATHROOM AT 1ST FLOOR AND NEW COVERED LANDING AT 1ST FLOOR
- Permit Issued
- Issued on 9/28/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2021 | COLIN LOREDO |
| Corrections Issued | 12/28/2021 | COLIN LOREDO |
| Quality Review Completed | 1/3/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 1/5/2022 | APPLICANT |
| Plan Check Approved | 3/9/2023 | SEAN SHAHMIRI |
| Issued | 9/28/2023 | APPLICANT |
| CofO in Progress | 2/7/2025 | JESUS RODRIGUEZ |
| CofO Issued | 2/12/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/12/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 1/14/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2022 | DINAH GARIN |
| Sewer availability | Cleared | 1/19/2022 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 2/10/2022 | DINAH GARIN |
| Construction within easement | Cleared | 2/23/2022 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 3/9/2023 | COLIN LOREDO |
Contact Information
| Contractor | Stout Design Build Inc; Lic. No.: 980007-B | 12405 VENICE BLVD 352 LOS ANGELES, CA 90066 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/1/2023 | Partial Inspection | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 12/1/2023 | Partial Inspection | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 12/18/2023 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2024 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2024 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 1/18/2024 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 1/23/2024 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/12/2024 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 3/12/2024 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 3/12/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 3/22/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Rough | 3/22/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 4/10/2024 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2024 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/10/2024 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/17/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 4/25/2024 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 5/2/2024 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 5/2/2024 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 5/2/2024 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/8/2024 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 5/8/2024 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 5/8/2024 | Approved | CARLOS MATAMOROS |
| Insulation | 5/24/2024 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2024 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 6/14/2024 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 6/24/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/29/2024 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Final | 11/20/2024 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 11/20/2024 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 11/22/2024 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 11/22/2024 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 12/4/2024 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 12/11/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 12/11/2024 | Approved | JESUS RODRIGUEZ |
| Final | 1/23/2025 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 1/23/2025 | Approved | JESUS RODRIGUEZ |
| Grading Pre-Inspection | 1/23/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Final | 1/23/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 1/23/2025 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 1/23/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 1/23/2025 | Approved | JESUS RODRIGUEZ |
| Final | 2/3/2025 | OK to Issue CofO | JESUS RODRIGUEZ |