1081 E NOWITA PL 90291

Certificate Information: 1081 E NOWITA PL 90291

Application / Permit
21014-20000-05885
Plan Check / Job No.
B21VN16221
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST AND 2ND FLOOR ADDITION WITH BALCONY TO THE (E) SINGLE FAMILY DWELLING. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/13/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/23/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 COLIN LOREDO
Corrections Issued 1/18/2022 COLIN LOREDO
Quality Review Completed 1/24/2022 OMID HEDAYAT
Building Plans Picked Up 1/27/2022 APPLICANT
Applicant returned to address corrections 5/27/2022 COLIN LOREDO
Plan Check Approved 6/1/2022 COLIN LOREDO
Issued 7/13/2022 APPLICANT
CofO in Progress 4/5/2024 HERBERT GIRON
Permit Finaled 4/8/2024 DANIEL ORRANTE
CofO Issued 4/8/2024 DANIEL ORRANTE
Permit Finaled 4/8/2024 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 1/31/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 2/15/2022 DINAH GARIN
Low Impact Development Cleared 5/12/2022 MICHAEL SCADUTO
Roof/Waste drainage to street Cleared 5/16/2022 DINAH GARIN

Contact Information

Contractor H H K C Development Inc; Lic. No.: 1045968-B P O BOX 205      SAN GABRIEL, CA 91778
Engineer Saberi,, Masoud; Lic. No.: C71553 1438 25TH ST APT 4      SANTA MONICA, CA 90404

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/16/2022 Approved EVAN COOPER
Gas Test 2/2/2023 Partial Approval HERBERT GIRON
PLUMBING-Rough 2/2/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/6/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 2/6/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/4/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/6/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/11/2023 Corrections Issued MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 5/19/2023 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/12/2023 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Partial Approval EVAN COOPER
Green Building Rough 7/17/2023 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/27/2023 Partial Approval EVAN COOPER
PLUMBING-Rough 7/27/2023 Not Ready for Inspection EVAN COOPER
Special/Order Compliance 7/27/2023 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 8/10/2023 Corrections Issued EVAN COOPER
PLUMBING-Rough 8/10/2023 Approved EVAN COOPER
ELECTRICAL-Rough 9/13/2023 Corrections Issued HERBERT GIRON
Shower Pan 9/13/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 9/21/2023 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 10/12/2023 Not Ready for Inspection HERBERT GIRON
Green Building Rough 10/12/2023 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 10/12/2023 Corrections Issued HERBERT GIRON
HVAC-Rough 10/25/2023 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 10/27/2023 Corrections Issued HERBERT GIRON
Green Building Rough 10/27/2023 Approved HERBERT GIRON
Verify Sprinkler Sign Off 10/27/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 11/15/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 11/15/2023 Partial Approval HERBERT GIRON
HVAC-Rough 11/28/2023 Approved TEMISTOCLES CAAL
Insulation 11/28/2023 Approved TEMISTOCLES CAAL
Drywall Nailing 12/13/2023 Approved HERBERT GIRON
PLUMBING-Final 12/13/2023 Corrections Issued HERBERT GIRON
Smoke Detectors 12/13/2023 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 1/3/2024 Partial Approval HERBERT GIRON
Shower Pan 1/3/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 1/8/2024 Approved HERBERT GIRON
Special/Order Compliance 1/8/2024 Partial Inspection BEN MOLSTAD
ELECTRICAL-Final 3/27/2024 Corrections Issued HERBERT GIRON
Green Building Final 3/27/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 3/27/2024 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 3/27/2024 SGSOV Not Ready HERBERT GIRON
Smoke Detectors 3/27/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 4/1/2024 Approved HERBERT GIRON
Green Building Final 4/1/2024 Approved HERBERT GIRON
HVAC-Final 4/1/2024 Approved HERBERT GIRON
PLUMBING-Final 4/1/2024 Corrections Issued HERBERT GIRON
Smoke Detectors 4/1/2024 Approved HERBERT GIRON
Final 4/5/2024 OK to Issue CofO HERBERT GIRON
PLUMBING-Final 4/5/2024 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 4/5/2024 SGSOV Approved HERBERT GIRON
Service/Power Release 4/5/2024 Approved HERBERT GIRON