1081 E NOWITA PL 90291
Certificate Information: 1081 E NOWITA PL 90291
- Application / Permit
- 21014-20000-05885
- Plan Check / Job No.
- B21VN16221
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST AND 2ND FLOOR ADDITION WITH BALCONY TO THE (E) SINGLE FAMILY DWELLING. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/13/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2022 | COLIN LOREDO |
| Corrections Issued | 1/18/2022 | COLIN LOREDO |
| Quality Review Completed | 1/24/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 1/27/2022 | APPLICANT |
| Applicant returned to address corrections | 5/27/2022 | COLIN LOREDO |
| Plan Check Approved | 6/1/2022 | COLIN LOREDO |
| Issued | 7/13/2022 | APPLICANT |
| CofO in Progress | 4/5/2024 | HERBERT GIRON |
| Permit Finaled | 4/8/2024 | DANIEL ORRANTE |
| CofO Issued | 4/8/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/8/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 1/31/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2022 | DINAH GARIN |
| Low Impact Development | Cleared | 5/12/2022 | MICHAEL SCADUTO |
| Roof/Waste drainage to street | Cleared | 5/16/2022 | DINAH GARIN |
Contact Information
| Contractor | H H K C Development Inc; Lic. No.: 1045968-B | P O BOX 205 SAN GABRIEL, CA 91778 |
| Engineer | Saberi,, Masoud; Lic. No.: C71553 | 1438 25TH ST APT 4 SANTA MONICA, CA 90404 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/16/2022 | Approved | EVAN COOPER |
| Gas Test | 2/2/2023 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 2/2/2023 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2023 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 2/6/2023 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2023 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2023 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Corrections Issued | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2023 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2023 | Partial Approval | EVAN COOPER |
| Green Building Rough | 7/17/2023 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2023 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 7/27/2023 | Not Ready for Inspection | EVAN COOPER |
| Special/Order Compliance | 7/27/2023 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 8/10/2023 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 8/10/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 9/13/2023 | Corrections Issued | HERBERT GIRON |
| Shower Pan | 9/13/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 9/21/2023 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 10/12/2023 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Rough | 10/12/2023 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Rough | 10/12/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 10/25/2023 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/27/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 10/27/2023 | Approved | HERBERT GIRON |
| Verify Sprinkler Sign Off | 10/27/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/15/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 11/15/2023 | Partial Approval | HERBERT GIRON |
| HVAC-Rough | 11/28/2023 | Approved | TEMISTOCLES CAAL |
| Insulation | 11/28/2023 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 12/13/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 12/13/2023 | Corrections Issued | HERBERT GIRON |
| Smoke Detectors | 12/13/2023 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 1/3/2024 | Partial Approval | HERBERT GIRON |
| Shower Pan | 1/3/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 1/8/2024 | Approved | HERBERT GIRON |
| Special/Order Compliance | 1/8/2024 | Partial Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 3/27/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 3/27/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 3/27/2024 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 3/27/2024 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 3/27/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 4/1/2024 | Approved | HERBERT GIRON |
| Green Building Final | 4/1/2024 | Approved | HERBERT GIRON |
| HVAC-Final | 4/1/2024 | Approved | HERBERT GIRON |
| PLUMBING-Final | 4/1/2024 | Corrections Issued | HERBERT GIRON |
| Smoke Detectors | 4/1/2024 | Approved | HERBERT GIRON |
| Final | 4/5/2024 | OK to Issue CofO | HERBERT GIRON |
| PLUMBING-Final | 4/5/2024 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 4/5/2024 | SGSOV Approved | HERBERT GIRON |
| Service/Power Release | 4/5/2024 | Approved | HERBERT GIRON |