12430 W KLING ST 91604

Certificate Information: 12430 W KLING ST 91604

Application / Permit
21014-20000-05884
Plan Check / Job No.
B21VN16219
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF BEDROOM/BATHROOM/LAUNDRY ROOM/DEN/FAMILY ROOM (IRR 43' X 37'-4") TO (E) 1-STORY SFD; MAJOR REMODEL; REFRAME ENTIRE ROOF (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 5/2/2022
Issuing Office
Current Status
CofO Issued on 5/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2021 APPLICANT
Assigned to Plan Check Engineer 12/29/2021 NILOOFAR MEHRAIN
Corrections Issued 1/25/2022 NILOOFAR MEHRAIN
Quality Review Completed 2/1/2022 STEVEN KIM
Building Plans Picked Up 2/3/2022 APPLICANT
Plan Check Approved 4/19/2022 NILOOFAR MEHRAIN
Issued 5/2/2022 APPLICANT
CofO in Progress 5/16/2023 CHRISTOPHE COCHRAN
Permit Finaled 5/16/2023 MICHAEL SMITH
CofO Issued 5/16/2023 MICHAEL SMITH
Permit Finaled 5/16/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/7/2022 CARLOS AGUILERA
Sewer availability Cleared 2/7/2022 CARLOS AGUILERA
ZI Cleared 2/7/2022 PABLO ESTRADA
Hydrant and Access approval Cleared 3/5/2022 CINDY JOSSELYN
Low Impact Development Cleared 3/22/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 3/31/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 2919 BURBANK BLVD STE D      BURBANK, CA 91505

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/30/2022 Conditional Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 8/30/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 9/6/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 9/23/2022 Partial Approval CHRISTOPHE COCHRAN
Underground Mechanical 9/23/2022 Approved CHRISTOPHE COCHRAN
Insulation 9/27/2022 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 9/28/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 9/29/2022 Partial Approval CHRISTOPHE COCHRAN
Pre-Inspection 9/29/2022 Approved CHRISTOPHE COCHRAN
Wood Frame 9/29/2022 Partial Approval CHRISTOPHE COCHRAN
Deputy Wood Construction 10/17/2022 Conditional Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 10/19/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 10/19/2022 Approved CHRISTOPHE COCHRAN
Shower Pan 10/24/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 11/10/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 11/10/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 11/10/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 11/17/2022 Approved MATTHEW NELSON
HVAC-Rough 11/17/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 11/21/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 11/21/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 11/21/2022 Partial Approval CHRISTOPHE COCHRAN
MERV13>=Rough 11/21/2022 Approved CHRISTOPHE COCHRAN
Insulation 11/23/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Insulation 12/9/2022 Approved CHRISTOPHE COCHRAN
Drywall Nailing 12/16/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/21/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/27/2022 Approved CHRISTOPHE COCHRAN
Underground Mechanical 12/27/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 4/20/2023 Corrections Issued CHRISTOPHE COCHRAN
Gas Test 4/20/2023 Approved CHRISTOPHE COCHRAN
Green Building Final 4/20/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Final 4/20/2023 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Final 4/20/2023 Approved CHRISTOPHE COCHRAN
Smoke Detectors 4/20/2023 Approved CHRISTOPHE COCHRAN
Final 5/5/2023 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/5/2023 Approved CHRISTOPHE COCHRAN
Green Building Final 5/5/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
MERV13>=Final 5/5/2023 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 5/5/2023 SGSOV Approved CHRISTOPHE COCHRAN
Final 5/16/2023 OK to Issue CofO CHRISTOPHE COCHRAN
Green Building Final 5/16/2023 Approved CHRISTOPHE COCHRAN