5910 N VESPER AVE 91411
Certificate Information: 5910 N VESPER AVE 91411
- Application / Permit
- 21014-20000-05876
- Plan Check / Job No.
- B21VN16193
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL & 35'2"X44'0" IRREGULAR SHAPED 1ST AND 2ND FLOOR ADDITIONS TO THE (E) SINGLE FAMILY DWELLING WITH 2ND FLOOR DECK. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 5/15/2024
- Issuing Office
- Current Status
- Issued on 5/15/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2022 | COLIN LOREDO |
| Corrections Issued | 1/18/2022 | COLIN LOREDO |
| Quality Review Completed | 1/26/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 1/26/2022 | APPLICANT |
| Applicant returned to address corrections | 2/29/2024 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 4/22/2024 | MARVEL DELACRUZ |
| Plan Check Approved | 5/10/2024 | MARVEL DELACRUZ |
| Issued | 5/15/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/8/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 1/27/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 1/27/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/31/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 6/4/2024 | Corrections Issued | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 6/5/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 7/19/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2024 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 7/19/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Sewer | 7/19/2024 | Approved | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 7/22/2024 | Conditional Approval | ROBERT GOLD |
| Deputy Steel/Welding | 7/22/2024 | Conditional Approval | ROBERT GOLD |
| PLUMBING-Rough | 7/24/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 7/24/2024 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 7/26/2024 | Partial Approval | KEVIN BERBERYAN |
| HVAC-Rough | 7/26/2024 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 7/26/2024 | Conditional Approval | KEVIN BERBERYAN |
| Deputy Wood Construction | 7/29/2024 | Conditional Approval | ROBERT GOLD |
| ELECTRICAL-Rough | 8/9/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 8/9/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 8/9/2024 | Approved | RYAN SALAZAR |
| Insulation | 9/3/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 9/10/2024 | Partial Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2024 | Corrections Issued | DAVID MATSON |
| Green Building Rough | 9/10/2024 | Corrections Issued | DAVID MATSON |
| BUILDING-Rough-Frame | 10/31/2024 | Approved | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 10/31/2024 | Conditional Approval | RAUL OLAGI |
| Green Building Rough | 10/31/2024 | Approved | RYAN SALAZAR |
| Shower Pan | 11/25/2024 | Approved | RYAN SALAZAR |