22025 W LEADWELL ST 91303

Certificate Information: 22025 W LEADWELL ST 91303

Application / Permit
21014-20000-05868
Plan Check / Job No.
B21VN16163
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 12' 6" X 15' 4" TO (E) DETACHED GARAGE AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 4/23/2022
Issuing Office
Current Status
CofO Issued on 2/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/23/2021 APPLICANT
Assigned to Plan Check Engineer 12/2/2021 GURUNATH NESARAJAH
Corrections Issued 12/4/2021 GURUNATH NESARAJAH
Plan Check Approved 4/4/2022 GURUNATH NESARAJAH
Building Plans Picked Up 4/7/2022 APPLICANT
Issued 4/23/2022 APPLICANT
CofO in Progress 1/11/2023 CHRIS CHRISTENSEN
CofO Issued 2/21/2023 JOHN JANSON
Permit Finaled 2/21/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/8/2021 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 12/8/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 12/20/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 12/20/2021 JOSE DUARTE-DIAZ
Construction near power lines Cleared 2/27/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/20/2022 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 5/20/2022 Partial Approval CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 5/27/2022 Conditional Approval KRISTEN CAUSEY
Underground Mechanical 5/27/2022 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/8/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/22/2022 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/22/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Rough 7/22/2022 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 7/22/2022 Corrections Issued CHRIS CHRISTENSEN
Wood Frame 7/22/2022 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/1/2022 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 8/1/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 8/1/2022 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 8/1/2022 Approved CHRIS CHRISTENSEN
Wood Frame 8/1/2022 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/10/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 8/10/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/10/2022 Partial Approval CHRIS CHRISTENSEN
Insulation 8/17/2022 Partial Approval JESUS PINEDA
Wood Frame 9/20/2022 Approved CHRIS CHRISTENSEN
Drywall Nailing 9/29/2022 Approved CHRIS CHRISTENSEN
Shower Pan 9/29/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/14/2022 Not Ready for Inspection JUSTIN HAWLEY
Interior/Exterior Lathing 10/26/2022 Approved JUSTIN HAWLEY
Final 12/28/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 12/28/2022 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 12/28/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 12/28/2022 Approved CHRIS CHRISTENSEN
Final 1/4/2023 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 1/4/2023 Approved CHRIS CHRISTENSEN
Final 1/10/2023 OK to Issue CofO CHRIS CHRISTENSEN