4836-4838 E MENDOTA AVE 90042

Certificate Information: 4836-4838 E MENDOTA AVE 90042

Application / Permit
21014-20000-05866
Plan Check / Job No.
B21VN16157
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL THROUGHOUT (E) SFD AND CONVERT (E) 10'-4" X 16'-6" STORAGE TO (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER ENGINEERING. SEE COMMENTS.
Permit Issued
Issued on 5/13/2022
Issuing Office
Current Status
CofO Issued on 10/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2021 APPLICANT
Assigned to Plan Check Engineer 12/1/2021 JENNIFER LEE
Corrections Issued 12/2/2021 JENNIFER LEE
Applicant returned to address corrections 3/15/2022 JENNIFER LEE
Plan Check Approved 3/23/2022 JENNIFER LEE
Issued 5/13/2022 APPLICANT
Building Plans Picked Up 5/16/2022 APPLICANT
CofO in Progress 10/28/2025 NICHOLAS LOPEZ
Permit Finaled 10/29/2025 DEROLD HAUFF
CofO Issued 10/29/2025 DEROLD HAUFF
Permit Finaled 10/29/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/3/2022 CINDY QI
Sewer availability Cleared 3/3/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 3/4/2022 CINDY QI
Grading Pre-Inspection Cleared 3/21/2022 VASIL MIHALEV

Contact Information

Contractor Owner-Builder       ,
Engineer Lee,, Richard C C; Lic. No.: S1371 19321 VANOWEN ST      RESEDA, CA 91335

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/1/2022 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/14/2022 Corrections Issued HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 4/25/2023 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 5/3/2023 Partial Inspection SCOTT FINNILA
Footing/Foundation/Slab 9/5/2023 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/2/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Special/Order Compliance 11/2/2023 Partial Inspection HAMIK HARTOUNIAN
HVAC-Rough 7/24/2024 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 7/24/2024 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 8/2/2024 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 8/5/2024 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 8/9/2024 Partial Approval THOMAS LOGRASSO
HVAC-Rough 8/22/2024 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 8/27/2024 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 9/25/2024 Partial Approval THOMAS LOGRASSO
Insulation 10/8/2024 Partial Approval THOMAS LOGRASSO
Interior/Exterior Lathing 10/8/2024 Not Ready for Inspection THOMAS LOGRASSO
Drywall Nailing 10/31/2024 Partial Approval THOMAS LOGRASSO
Interior/Exterior Lathing 10/31/2024 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Rough 11/20/2024 Approved THOMAS LOGRASSO
HVAC-Rough 11/20/2024 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 11/20/2024 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 11/20/2024 Approved THOMAS LOGRASSO
Sewer 11/20/2024 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 4/22/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 4/22/2025 Approved NICHOLAS LOPEZ
Green Building Rough 4/22/2025 Approved NICHOLAS LOPEZ
Sewer 4/22/2025 Approved NICHOLAS LOPEZ
Gas Test 5/13/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 5/13/2025 Approved NICHOLAS LOPEZ
Final 9/17/2025 Corrections Issued NICHOLAS LOPEZ
Footing/Foundation/Slab 9/17/2025 Approved NICHOLAS LOPEZ
Green Building Final 9/17/2025 Not Ready for Inspection NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 9/17/2025 SGSOV Approved NICHOLAS LOPEZ
Smoke Detectors 9/17/2025 Approved NICHOLAS LOPEZ
Final 10/27/2025 OK to Issue CofO NICHOLAS LOPEZ
Green Building Final 10/27/2025 Approved NICHOLAS LOPEZ