14018 W CALVERT ST 91401

Certificate Information: 14018 W CALVERT ST 91401

Application / Permit
21014-20000-05861
Plan Check / Job No.
B21VN16147
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 11'-5" X 19'-4" FOR (N) BEDROOM TO AN (E) 1-STORY SFD. ALL WORK PER WFPP.
Permit Issued
Issued on 2/9/2022
Issuing Office
Current Status
CofO Issued on 4/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/23/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 JENNIFER LEE
Corrections Issued 12/1/2021 JENNIFER LEE
Applicant returned to address corrections 1/24/2022 JENNIFER LEE
Plan Check Approved 2/7/2022 JENNIFER LEE
Issued 2/9/2022 APPLICANT
Building Plans Picked Up 2/24/2022 APPLICANT
CofO in Progress 2/27/2024 RYAN SALAZAR
Permit Finaled 4/15/2024 DANIEL ORRANTE
CofO Issued 4/15/2024 DANIEL ORRANTE
Permit Finaled 4/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/19/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/24/2022 LEE GUILBEAUX
Sewer availability Cleared 1/24/2022 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/24/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/31/2023 Partial Inspection RYAN SALAZAR
Pre-Inspection 3/14/2023 Partial Inspection RYAN SALAZAR
Pre-Inspection 4/27/2023 Partial Approval RYAN SALAZAR
Deputy Drilled-In Anchors 5/1/2023 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 5/3/2023 Approved RYAN SALAZAR
Footing/Foundation/Slab 5/3/2023 Approved RYAN SALAZAR
Pre-Inspection 5/3/2023 Partial Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 5/11/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 5/26/2023 Partial Approval RYAN SALAZAR
Green Building Rough 5/26/2023 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 5/30/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 5/30/2023 Approved RYAN SALAZAR
Green Building Rough 5/30/2023 Approved RYAN SALAZAR
Insulation 6/8/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 6/8/2023 Partial Approval RYAN SALAZAR
Drywall Nailing 6/22/2023 Approved RYAN SALAZAR
Final 2/23/2024 OK to Issue CofO RYAN SALAZAR
Green Building Final 2/23/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 2/23/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 2/23/2024 Approved RYAN SALAZAR