8045 N DARBY AVE 1-3 91335
Certificate Information: 8045 N DARBY AVE 1-3 91335
- Application / Permit
- 21014-20000-05854
- Plan Check / Job No.
- B21VN16134
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE TO J.A.D.U.
- Permit Issued
- Issued on 2/3/2022
- Issuing Office
- Current Status
- CofO Issued on 5/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | JOE VO |
| Corrections Issued | 11/25/2021 | JOE VO |
| Applicant returned to address corrections | 12/3/2021 | JOE VO |
| Plan Check Approved | 1/31/2022 | JOE VO |
| Issued | 2/3/2022 | APPLICANT |
| CofO in Progress | 5/17/2022 | VINCENT HANLEY |
| Permit Finaled | 5/17/2022 | MICHAEL SMITH |
| CofO Issued | 5/17/2022 | MICHAEL SMITH |
| Permit Finaled | 5/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/29/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/30/2021 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 1/31/2022 | JOE VO |
Contact Information
| Contractor | D H R Builders Inc; Lic. No.: 1054047-B | 18336 DELANO STREET TARZANA, CA 91335 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/9/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 2/9/2022 | Partial Approval | VINCENT HANLEY |
| Sewer | 2/9/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/24/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/24/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 2/24/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 2/24/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/24/2022 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 2/24/2022 | Approved | VINCENT HANLEY |
| Shower Pan | 2/24/2022 | Approved | VINCENT HANLEY |
| Insulation | 3/3/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/3/2022 | Approved | VINCENT HANLEY |
| Drywall Nailing | 3/9/2022 | Approved | JESUS PINEDA |
| Drywall Nailing | 3/14/2022 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 4/27/2022 | Corrections Issued | VINCENT HANLEY |
| Final | 4/27/2022 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 4/27/2022 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 4/27/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 4/27/2022 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 4/27/2022 | Corrections Issued | VINCENT HANLEY |
| Smoke Detectors | 4/27/2022 | Approved | VINCENT HANLEY |
| Service/Power Release | 5/4/2022 | No Access for Inspection | VINCENT HANLEY |
| ELECTRICAL-Final | 5/5/2022 | Approved | VINCENT HANLEY |
| Final | 5/5/2022 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 5/5/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 5/5/2022 | Approved | VINCENT HANLEY |
| Service/Power Release | 5/5/2022 | Approved | VINCENT HANLEY |
| Final | 5/17/2022 | OK to Issue CofO | VINCENT HANLEY |