18751 W VICTORY BLVD 91335
Certificate Information: 18751 W VICTORY BLVD 91335
- Application / Permit
- 21014-20000-05824
- Plan Check / Job No.
- B21VN16058
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 22' x 39'-6" (869 sf) ADDITION OF A (N) ACCESSORY DWELLING UNIT ATTACHED TO THE (E) DET. GARAGE PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 1/28/2022
- Issuing Office
- Current Status
- CofO Issued on 5/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2021 | JESSE ARELLANO |
| Corrections Issued | 11/30/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 1/12/2022 | ANGELICA DAVE |
| Applicant returned to address corrections | 1/25/2022 | ANGELICA DAVE |
| Issued | 1/28/2022 | APPLICANT |
| Building Plans Picked Up | 1/28/2022 | APPLICANT |
| CofO in Progress | 5/13/2022 | SEAN HAUPT |
| Permit Finaled | 5/24/2022 | MICHAEL SMITH |
| CofO Issued | 5/24/2022 | MICHAEL SMITH |
| Permit Finaled | 5/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2021 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2021 | AMIR KASHFI |
| Sewer availability | Cleared | 12/9/2021 | AMIR KASHFI |
| ZI | Cleared | 12/20/2021 | LAUREN PADICK |
| Low Impact Development | Cleared | 12/29/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 12/29/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/31/2022 | Approved | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 2/3/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 2/28/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 2/28/2022 | Not Ready for Inspection | SEAN HAUPT |
| Rough-Elec/Plmb/HVAC | 2/28/2022 | Approved | SEAN HAUPT |
| Underground Mechanical | 2/28/2022 | Approved | SEAN HAUPT |
| Wood Frame | 2/28/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2022 | Not Ready for Inspection | SEAN HAUPT |
| Interior/Exterior Lathing | 3/2/2022 | Approved | SEAN HAUPT |
| Wood Frame | 3/2/2022 | Not Ready for Inspection | SEAN HAUPT |
| Insulation | 3/4/2022 | Approved | SEAN HAUPT |
| Shower Pan | 3/4/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 3/10/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 3/10/2022 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 3/11/2022 | No Access for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 3/11/2022 | No Access for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/25/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 4/25/2022 | Corrections Issued | SEAN HAUPT |
| Final | 4/25/2022 | Corrections Issued | SEAN HAUPT |
| Footing/Foundation/Slab | 4/25/2022 | Approved | SEAN HAUPT |
| Green Building Final | 4/25/2022 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 4/25/2022 | Approved | SEAN HAUPT |
| HVAC-Final | 4/25/2022 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Final | 4/25/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 4/25/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 4/25/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 5/13/2022 | Approved | SEAN HAUPT |
| Final | 5/13/2022 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 5/13/2022 | Approved | SEAN HAUPT |
| HVAC-Final | 5/13/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 5/13/2022 | Approved | SEAN HAUPT |