18751 W VICTORY BLVD 91335

Certificate Information: 18751 W VICTORY BLVD 91335

Application / Permit
21014-20000-05824
Plan Check / Job No.
B21VN16058
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
22' x 39'-6" (869 sf) ADDITION OF A (N) ACCESSORY DWELLING UNIT ATTACHED TO THE (E) DET. GARAGE PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 1/28/2022
Issuing Office
Current Status
CofO Issued on 5/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2021 APPLICANT
Assigned to Plan Check Engineer 11/30/2021 JESSE ARELLANO
Corrections Issued 11/30/2021 JESSE ARELLANO
Applicant returned to address corrections 1/12/2022 ANGELICA DAVE
Applicant returned to address corrections 1/25/2022 ANGELICA DAVE
Issued 1/28/2022 APPLICANT
Building Plans Picked Up 1/28/2022 APPLICANT
CofO in Progress 5/13/2022 SEAN HAUPT
Permit Finaled 5/24/2022 MICHAEL SMITH
CofO Issued 5/24/2022 MICHAEL SMITH
Permit Finaled 5/24/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/3/2021 AMIR KASHFI
Eng Process Fee Ord 176,300 Cleared 12/3/2021 AMIR KASHFI
Sewer availability Cleared 12/9/2021 AMIR KASHFI
ZI Cleared 12/20/2021 LAUREN PADICK
Low Impact Development Cleared 12/29/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/29/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/31/2022 Approved JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 2/3/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/16/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 2/28/2022 Approved SEAN HAUPT
Green Building Rough 2/28/2022 Not Ready for Inspection SEAN HAUPT
Rough-Elec/Plmb/HVAC 2/28/2022 Approved SEAN HAUPT
Underground Mechanical 2/28/2022 Approved SEAN HAUPT
Wood Frame 2/28/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 3/2/2022 Not Ready for Inspection SEAN HAUPT
Interior/Exterior Lathing 3/2/2022 Approved SEAN HAUPT
Wood Frame 3/2/2022 Not Ready for Inspection SEAN HAUPT
Insulation 3/4/2022 Approved SEAN HAUPT
Shower Pan 3/4/2022 Approved SEAN HAUPT
Drywall Nailing 3/10/2022 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 3/10/2022 Approved KRISTEN CAUSEY
Drywall Nailing 3/11/2022 No Access for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 3/11/2022 No Access for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 4/25/2022 Approved SEAN HAUPT
ELECTRICAL-Final 4/25/2022 Corrections Issued SEAN HAUPT
Final 4/25/2022 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 4/25/2022 Approved SEAN HAUPT
Green Building Final 4/25/2022 Not Ready for Inspection SEAN HAUPT
Green Building Rough 4/25/2022 Approved SEAN HAUPT
HVAC-Final 4/25/2022 Corrections Issued SEAN HAUPT
PLUMBING-Final 4/25/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 4/25/2022 SGSOV Approved SEAN HAUPT
Smoke Detectors 4/25/2022 Approved SEAN HAUPT
ELECTRICAL-Final 5/13/2022 Approved SEAN HAUPT
Final 5/13/2022 OK to Issue CofO SEAN HAUPT
Green Building Final 5/13/2022 Approved SEAN HAUPT
HVAC-Final 5/13/2022 Approved SEAN HAUPT
PLUMBING-Final 5/13/2022 Approved SEAN HAUPT