13849 W CHASE ST 1-23 91402

Certificate Information: 13849 W CHASE ST 1-23 91402

Application / Permit
21014-20000-05823
Plan Check / Job No.
B21VN16054
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Convert existing attached carport into three (3) ADUs of (e) apartment building. Per State code GCS 65852.2(e)(1)(C)
Permit Issued
Issued on 6/27/2022
Issuing Office
Current Status
CofO Issued on 5/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/23/2021 APPLICANT
Assigned to Plan Check Engineer 12/22/2021 JOE VO
Corrections Issued 12/25/2021 JOE VO
Quality Review Completed 12/28/2021 LIPING TENG
Applicant returned to address corrections 2/14/2022 JOE VO
Applicant returned to address corrections 5/24/2022 JOE VO
Plan Check Approved 6/8/2022 JOE VO
Issued 6/27/2022 APPLICANT
CofO in Progress 5/23/2023 ANDREW DORSO
Permit Finaled 5/25/2023 JEFFREY DURAN
CofO Issued 5/25/2023 JEFFREY DURAN
Permit Finaled 5/25/2023 JEFFREY DURAN

Permit Application Clearance Information

Address approval Cleared 1/6/2022 LEE GUILBEAUX
Sewer availability Cleared 1/6/2022 LEE GUILBEAUX
Tenant Habitability Plan Cleared 1/6/2022 RICHARD BRINSON
Eng Process Fee Ord 176,300 Cleared 2/25/2022 CARLOS AGUILERA
Green Code Cleared 3/15/2022 JOE VO
Hydrant and Access approval Cleared 3/20/2022 CINDY JOSSELYN
DAS Clearance Cleared 5/24/2022 JOE VO
Fire Marshal Fire Life Safety Cleared 5/24/2022 VIDAL GARCIA
"Q" conditions Cleared 5/30/2022 STEVEN WECHSLER

Contact Information

Architect Suayan,, Rey D; Lic. No.: NA37726       ,
Contractor Rent Ready Construction Inc; Lic. No.: 1065376-B       ,
Engineer Tuna,, Suleyman; Lic. No.: NA73294       ,

Inspector Information

ANDREW DORSO, (818) 374-7520 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/17/2023 Conditional Approval ANDREW DORSO
Footing/Foundation/Slab 1/26/2023 Approved ANDREW DORSO
Special/Order Compliance 1/26/2023 Approved STEVEN LEVITT
Deputy Wood Construction 2/14/2023 Conditional Approval ANDREW DORSO
Special/Order Compliance 2/14/2023 Conditional Approval STEVEN LEVITT
Green Building Rough 2/23/2023 Approved ANDREW DORSO
Wood Frame 2/23/2023 Partial Inspection ANDREW DORSO
Insulation 3/6/2023 Approved ANDREW DORSO
Interior/Exterior Lathing 3/6/2023 Partial Inspection ANDREW DORSO
Drywall Nailing 3/10/2023 Approved ANDREW DORSO
Interior/Exterior Lathing 3/10/2023 Approved ANDREW DORSO
Final 5/19/2023 Partial Inspection ANDREW DORSO
Green Building Final 5/19/2023 Approved ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 5/19/2023 SGSOV Approved ANDREW DORSO
Smoke Detectors 5/19/2023 Approved ANDREW DORSO
Wood Frame 5/19/2023 Approved ANDREW DORSO
Final 5/23/2023 OK to Issue CofO ANDREW DORSO