13849 W CHASE ST 1-23 91402
Certificate Information: 13849 W CHASE ST 1-23 91402
- Application / Permit
- 21014-20000-05823
- Plan Check / Job No.
- B21VN16054
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Convert existing attached carport into three (3) ADUs of (e) apartment building. Per State code GCS 65852.2(e)(1)(C)
- Permit Issued
- Issued on 6/27/2022
- Issuing Office
- Current Status
- CofO Issued on 5/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2021 | JOE VO |
| Corrections Issued | 12/25/2021 | JOE VO |
| Quality Review Completed | 12/28/2021 | LIPING TENG |
| Applicant returned to address corrections | 2/14/2022 | JOE VO |
| Applicant returned to address corrections | 5/24/2022 | JOE VO |
| Plan Check Approved | 6/8/2022 | JOE VO |
| Issued | 6/27/2022 | APPLICANT |
| CofO in Progress | 5/23/2023 | ANDREW DORSO |
| Permit Finaled | 5/25/2023 | JEFFREY DURAN |
| CofO Issued | 5/25/2023 | JEFFREY DURAN |
| Permit Finaled | 5/25/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/6/2022 | LEE GUILBEAUX |
| Tenant Habitability Plan | Cleared | 1/6/2022 | RICHARD BRINSON |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2022 | CARLOS AGUILERA |
| Green Code | Cleared | 3/15/2022 | JOE VO |
| Hydrant and Access approval | Cleared | 3/20/2022 | CINDY JOSSELYN |
| DAS Clearance | Cleared | 5/24/2022 | JOE VO |
| Fire Marshal Fire Life Safety | Cleared | 5/24/2022 | VIDAL GARCIA |
| "Q" conditions | Cleared | 5/30/2022 | STEVEN WECHSLER |
Contact Information
| Architect | Suayan,, Rey D; Lic. No.: NA37726 | , |
| Contractor | Rent Ready Construction Inc; Lic. No.: 1065376-B | , |
| Engineer | Tuna,, Suleyman; Lic. No.: NA73294 | , |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/17/2023 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 1/26/2023 | Approved | ANDREW DORSO |
| Special/Order Compliance | 1/26/2023 | Approved | STEVEN LEVITT |
| Deputy Wood Construction | 2/14/2023 | Conditional Approval | ANDREW DORSO |
| Special/Order Compliance | 2/14/2023 | Conditional Approval | STEVEN LEVITT |
| Green Building Rough | 2/23/2023 | Approved | ANDREW DORSO |
| Wood Frame | 2/23/2023 | Partial Inspection | ANDREW DORSO |
| Insulation | 3/6/2023 | Approved | ANDREW DORSO |
| Interior/Exterior Lathing | 3/6/2023 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 3/10/2023 | Approved | ANDREW DORSO |
| Interior/Exterior Lathing | 3/10/2023 | Approved | ANDREW DORSO |
| Final | 5/19/2023 | Partial Inspection | ANDREW DORSO |
| Green Building Final | 5/19/2023 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 5/19/2023 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 5/19/2023 | Approved | ANDREW DORSO |
| Wood Frame | 5/19/2023 | Approved | ANDREW DORSO |
| Final | 5/23/2023 | OK to Issue CofO | ANDREW DORSO |