5847 N TOBIAS AVE 91411

Certificate Information: 5847 N TOBIAS AVE 91411

Application / Permit
21014-20000-05813
Plan Check / Job No.
B21VN16026
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 2 STORY TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d); EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 6/24/2022
Issuing Office
Current Status
CofO Issued on 10/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2021 APPLICANT
Assigned to Plan Check Engineer 12/2/2021 SELLA BENYAMIN
Corrections Issued 12/7/2021 SELLA BENYAMIN
Quality Review Completed 12/10/2021 STEVEN KIM
Building Plans Picked Up 12/10/2021 APPLICANT
Plan Check Approved 6/2/2022 SELLA BENYAMIN
Issued 6/24/2022 APPLICANT
CofO in Progress 9/11/2024 RYAN SALAZAR
Permit Finaled 10/3/2024 DANIEL ORRANTE
CofO Issued 10/3/2024 DANIEL ORRANTE
Permit Finaled 10/3/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/8/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 3/9/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 3/9/2022 JOSE DUARTE-DIAZ
Construction near power lines Cleared 4/19/2022 RIDWAN HARDY
Low Impact Development Cleared 5/12/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 5/17/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/16/2022 Partial Approval RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 9/22/2022 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 9/28/2022 Approved RICHARD DOCKUS
Gas Test 2/10/2023 Approved RYAN SALAZAR
PLUMBING-Rough 2/10/2023 Approved RYAN SALAZAR
Sewer 2/10/2023 Approved RYAN SALAZAR
Underground Mechanical 2/10/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 2/24/2023 Approved RYAN SALAZAR
Green Building Rough 2/24/2023 Not Ready for Inspection RYAN SALAZAR
Wood Frame 2/24/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 4/5/2023 Partial Inspection RYAN SALAZAR
Green Building Rough 4/5/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/5/2023 Conditional Approval RYAN SALAZAR
Shower Pan 4/5/2023 Approved RYAN SALAZAR
Wood Frame 4/5/2023 Corrections Issued RYAN SALAZAR
BUILDING-Rough-Frame 4/27/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/27/2023 Approved RYAN SALAZAR
Wood Frame 4/27/2023 Approved RYAN SALAZAR
HVAC-Rough 7/13/2023 Approved RYAN SALAZAR
Insulation 7/18/2023 Approved RYAN SALAZAR
Drywall Nailing 8/18/2023 Approved RYAN SALAZAR
Final 6/6/2024 Corrections Issued RYAN SALAZAR
Green Building Final 6/6/2024 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 6/6/2024 SGSOV Not Ready RYAN SALAZAR
Smoke Detectors 6/6/2024 Approved RYAN SALAZAR
ELECTRICAL-Final 9/9/2024 Approved RYAN SALAZAR
Final 9/9/2024 OK to Issue CofO RYAN SALAZAR
Green Building Final 9/9/2024 Approved RYAN SALAZAR
HVAC-Final 9/9/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 9/9/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 9/9/2024 Approved RYAN SALAZAR