734 W 78TH ST 90044

Certificate Information: 734 W 78TH ST 90044

Application / Permit
21014-20000-05809
Plan Check / Job No.
B21VN16018
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
33' X 41' (917 SQ. FT.) IRREGULAR SHAPED ADDITION TO AND CONVERT THE (E) 146 SQ. FT. STORAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)¹, (d)¹. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/17/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2021 APPLICANT
Assigned to Plan Check Engineer 11/29/2021 OMAR GARNICA
Corrections Issued 11/30/2021 OMAR GARNICA
Plan Check Approved 3/9/2022 OMAR GARNICA
Issued 3/17/2022 APPLICANT
Building Plans Picked Up 3/30/2022 APPLICANT
CofO in Progress 3/2/2023 LILIANA PORTILLO
CofO in Progress 3/2/2023 LILIANA PORTILLO
Permit Finaled 3/11/2023 DEROLD HAUFF
CofO Issued 3/11/2023 DEROLD HAUFF
Permit Finaled 3/11/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/9/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 12/13/2021 STEVE MELGAR
Sewer availability Cleared 12/13/2021 STEVE MELGAR
Low Impact Development Cleared 1/31/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/22/2022 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/5/2022 Partial Approval LILIANA PORTILLO
Deputy Drilled-In Anchors 4/7/2022 Approved LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 4/7/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 4/7/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 4/13/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/6/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 5/6/2022 Approved LILIANA PORTILLO
Deputy Wood Construction 5/9/2022 Conditional Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 5/19/2022 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/19/2022 Approved LILIANA PORTILLO
HVAC-Rough 5/19/2022 Approved LILIANA PORTILLO
Underground Mechanical 5/19/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 5/23/2022 Approved LILIANA PORTILLO
Sewer 5/23/2022 Corrections Issued LILIANA PORTILLO
Underground Mechanical 5/23/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 5/26/2022 Approved HORACE FULTZ
Green Building Rough 5/26/2022 Approved HORACE FULTZ
Interior/Exterior Lathing 5/26/2022 Partial Approval HORACE FULTZ
Insulation 6/6/2022 Corrections Issued LILIANA PORTILLO
Insulation 6/10/2022 Conditional Approval LILIANA PORTILLO
Special/Order Compliance 6/10/2022 Partial Inspection SHAVONNE ESPINOZA
Drywall Nailing 6/15/2022 Corrections Issued LILIANA PORTILLO
Drywall Nailing 7/6/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 7/6/2022 Approved LILIANA PORTILLO
Shower Pan 7/6/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 2/21/2023 Approved LILIANA PORTILLO
Final 2/21/2023 Corrections Issued LILIANA PORTILLO
Green Building Final 2/21/2023 Corrections Issued LILIANA PORTILLO
HVAC-Final 2/21/2023 Approved LILIANA PORTILLO
PLUMBING-Final 2/21/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 2/21/2023 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 2/21/2023 Approved LILIANA PORTILLO
PLUMBING-Final 2/24/2023 Approved LILIANA PORTILLO
Final 2/28/2023 OK to Issue CofO LILIANA PORTILLO
Green Building Final 2/28/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 2/28/2023 SGSOV Approved LILIANA PORTILLO
Service/Power Release 2/28/2023 Approved LILIANA PORTILLO