734 W 78TH ST 90044
Certificate Information: 734 W 78TH ST 90044
- Application / Permit
- 21014-20000-05809
- Plan Check / Job No.
- B21VN16018
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 33' X 41' (917 SQ. FT.) IRREGULAR SHAPED ADDITION TO AND CONVERT THE (E) 146 SQ. FT. STORAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)¹, (d)¹. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2021 | OMAR GARNICA |
| Corrections Issued | 11/30/2021 | OMAR GARNICA |
| Plan Check Approved | 3/9/2022 | OMAR GARNICA |
| Issued | 3/17/2022 | APPLICANT |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| CofO in Progress | 3/2/2023 | LILIANA PORTILLO |
| CofO in Progress | 3/2/2023 | LILIANA PORTILLO |
| Permit Finaled | 3/11/2023 | DEROLD HAUFF |
| CofO Issued | 3/11/2023 | DEROLD HAUFF |
| Permit Finaled | 3/11/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 12/13/2021 | STEVE MELGAR |
| Low Impact Development | Cleared | 1/31/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 2/22/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/5/2022 | Partial Approval | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 4/7/2022 | Approved | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 4/7/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 4/7/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 4/13/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 5/6/2022 | Approved | LILIANA PORTILLO |
| Deputy Wood Construction | 5/9/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 5/19/2022 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 5/19/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 5/19/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 5/23/2022 | Approved | LILIANA PORTILLO |
| Sewer | 5/23/2022 | Corrections Issued | LILIANA PORTILLO |
| Underground Mechanical | 5/23/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/26/2022 | Approved | HORACE FULTZ |
| Green Building Rough | 5/26/2022 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 5/26/2022 | Partial Approval | HORACE FULTZ |
| Insulation | 6/6/2022 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 6/10/2022 | Conditional Approval | LILIANA PORTILLO |
| Special/Order Compliance | 6/10/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| Drywall Nailing | 6/15/2022 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 7/6/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 7/6/2022 | Approved | LILIANA PORTILLO |
| Shower Pan | 7/6/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 2/21/2023 | Approved | LILIANA PORTILLO |
| Final | 2/21/2023 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 2/21/2023 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 2/21/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 2/21/2023 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 2/21/2023 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 2/21/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 2/24/2023 | Approved | LILIANA PORTILLO |
| Final | 2/28/2023 | OK to Issue CofO | LILIANA PORTILLO |
| Green Building Final | 2/28/2023 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 2/28/2023 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 2/28/2023 | Approved | LILIANA PORTILLO |