8357-8359 N DONNA AVE 91324

Certificate Information: 8357-8359 N DONNA AVE 91324

Application / Permit
21014-20000-05795
Plan Check / Job No.
B21VN15971
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan PROPOSED ADDITION TO EXISTING SFD/ADU TO EXPAND EXISTING ADU.
Permit Issued
Issued on 2/1/2022
Issuing Office
Current Status
CofO Issued on 8/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 MICHAEL LOPEZ
Corrections Issued 11/25/2021 MICHAEL LOPEZ
Applicant returned to address corrections 12/17/2021 MICHAEL LOPEZ
Applicant returned to address corrections 1/6/2022 MICHAEL LOPEZ
Plan Check Approved 1/23/2022 MICHAEL LOPEZ
Issued 2/1/2022 APPLICANT
CofO in Progress 6/15/2022 JEFFREY PARD
CofO Issued 8/23/2022 JOHN JANSON
Permit Finaled 8/23/2022 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/20/2021 AMIR KASHFI
Eng Process Fee Ord 176,300 Cleared 12/21/2021 AMIR KASHFI
Sewer availability Cleared 12/27/2021 JOSE DUARTE-DIAZ

Contact Information

Contractor A E K Construction; Lic. No.: 819703-B 8357 DONNA AVE      NORTHRIDGE, CA 91324
Engineer Nguyen,, Quynh Anh; Lic. No.: C58592 12000 MIRANDA ST      VALLEY VILLAGE, CA 91607

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/28/2022 Approved JEFFREY PARD
Footing/Foundation/Slab 3/3/2022 Approved JEFFREY PARD
ELECTRICAL-Rough 3/24/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/24/2022 Approved VINCENT HANLEY
Green Building Rough 3/24/2022 Not Ready for Inspection VINCENT HANLEY
Insulation 3/24/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 3/24/2022 Approved VINCENT HANLEY
Underground Mechanical 3/24/2022 Approved VINCENT HANLEY
Wood Frame 3/24/2022 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 4/11/2022 Approved JEFFREY PARD
Green Building Rough 4/11/2022 Approved JEFFREY PARD
HVAC-Rough 4/11/2022 Approved JEFFREY PARD
Insulation 4/11/2022 Approved JEFFREY PARD
Interior/Exterior Lathing 4/11/2022 Approved JEFFREY PARD
Shower Pan 4/11/2022 Approved JEFFREY PARD
Drywall Nailing 4/15/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 4/15/2022 Approved JUSTIN HAWLEY
ELECTRICAL-Final 6/7/2022 Approved JEFFREY PARD
Final 6/7/2022 Corrections Issued JEFFREY PARD
Green Building Final 6/7/2022 Approved JEFFREY PARD
HVAC-Final 6/7/2022 Approved JEFFREY PARD
PLUMBING-Final 6/7/2022 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 6/7/2022 SGSOV Approved JEFFREY PARD
Smoke Detectors 6/7/2022 Approved JEFFREY PARD
Final 6/13/2022 OK to Issue CofO JEFFREY PARD