14205 W COHASSET ST 91405
Certificate Information: 14205 W COHASSET ST 91405
- Application / Permit
- 21014-20000-05783
- Plan Check / Job No.
- B21VN15941
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 16' 6" X 28' 8" REAR ADDITION TO (E) SFD, REMODEL TO RELOCATE KITCHEN & LAUNDRY AND ADD (1) POWDER ROOM & BATHROOM. ALL WORK DONE PER ENGINEERING. "COMPLY WITH DEPARTMENT ORDER effective date 07/20/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 7/19/2022
- Issuing Office
- Current Status
- CofO Issued on 5/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 11/30/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 6/30/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 7/13/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 7/15/2022 | APPLICANT |
| Issued | 7/19/2022 | APPLICANT |
| CofO in Progress | 1/29/2024 | BRYAN MEYER |
| CofO in Progress | 1/29/2024 | BRYAN MEYER |
| Permit Finaled | 5/7/2024 | DAVID JAMES |
| CofO Issued | 5/7/2024 | DAVID JAMES |
| Permit Finaled | 5/7/2024 | DAVID JAMES |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/6/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/8/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/28/2022 | Not Ready for Inspection | FELIPE PENICHE |
| ELECTRICAL-Rough | 7/28/2022 | Not Ready for Inspection | FELIPE PENICHE |
| Footing/Foundation/Slab | 7/28/2022 | Corrections Issued | FELIPE PENICHE |
| Green Building Rough | 7/28/2022 | Not Ready for Inspection | FELIPE PENICHE |
| BUILDING-Rough-Frame | 8/1/2022 | Corrections Issued | KIM BEAUCHAMP |
| ELECTRICAL-Rough | 8/1/2022 | Not Ready for Inspection | BRYAN MEYER |
| Footing/Foundation/Slab | 8/1/2022 | Corrections Issued | KIM BEAUCHAMP |
| Green Building Rough | 8/1/2022 | Not Ready for Inspection | KIM BEAUCHAMP |
| HVAC-Rough | 8/1/2022 | Not Ready for Inspection | BRYAN MEYER |
| PLUMBING-Rough | 8/1/2022 | Not Ready for Inspection | BRYAN MEYER |
| Footing/Foundation/Slab | 8/24/2022 | Corrections Issued | KIM BEAUCHAMP |
| Footing/Foundation/Slab | 9/12/2022 | Corrections Issued | KIM BEAUCHAMP |
| PLUMBING-Rough | 9/12/2022 | Not Ready for Inspection | KIM BEAUCHAMP |
| Excavation/Setback/Form/Re-Bar | 9/19/2022 | Not Ready for Inspection | DAVID HICKMAN |
| Footing/Foundation/Slab | 9/19/2022 | Not Ready for Inspection | DAVID HICKMAN |
| Underground Mechanical | 9/19/2022 | Not Ready for Inspection | DAVID HICKMAN |
| ELECTRICAL-Rough | 11/2/2022 | Corrections Issued | BRYAN MEYER |
| Footing/Foundation/Slab | 11/2/2022 | Corrections Issued | KIM BEAUCHAMP |
| HVAC-Rough | 11/2/2022 | Corrections Issued | BRYAN MEYER |
| PLUMBING-Rough | 11/2/2022 | Corrections Issued | BRYAN MEYER |
| Wood Frame | 11/2/2022 | Corrections Issued | KIM BEAUCHAMP |
| BUILDING-Rough-Frame | 11/22/2022 | Corrections Issued | KIM BEAUCHAMP |
| ELECTRICAL-Rough | 11/22/2022 | Corrections Issued | KIM BEAUCHAMP |
| Footing/Foundation/Slab | 11/22/2022 | Corrections Issued | KIM BEAUCHAMP |
| HVAC-Rough | 11/22/2022 | Not Ready for Inspection | KIM BEAUCHAMP |
| PLUMBING-Rough | 11/22/2022 | Not Ready for Inspection | KIM BEAUCHAMP |
| Deputy Drilled-In Anchors | 12/7/2022 | Conditional Approval | BRYAN MEYER |
| BUILDING-Rough-Frame | 12/20/2022 | Corrections Issued | BRYAN MEYER |
| ELECTRICAL-Rough | 12/20/2022 | Corrections Issued | KIM BEAUCHAMP |
| Footing/Foundation/Slab | 12/20/2022 | Corrections Issued | BRYAN MEYER |
| Green Building Rough | 12/20/2022 | Corrections Issued | KIM BEAUCHAMP |
| HVAC-Rough | 12/20/2022 | Corrections Issued | KIM BEAUCHAMP |
| PLUMBING-Rough | 12/20/2022 | Corrections Issued | BRYAN MEYER |
| BUILDING-Rough-Frame | 1/23/2023 | Partial Inspection | BRYAN MEYER |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Not Ready for Inspection | BRYAN MEYER |
| Green Building Rough | 1/23/2023 | Not Ready for Inspection | BRYAN MEYER |
| Rough-Elec/Plmb/HVAC | 1/23/2023 | Partial Inspection | BRYAN MEYER |
| Wood Frame | 1/30/2023 | Corrections Issued | BRYAN MEYER |
| BUILDING-Rough-Frame | 3/23/2023 | Corrections Issued | KIM BEAUCHAMP |
| Green Building Rough | 3/23/2023 | Not Ready for Inspection | KIM BEAUCHAMP |
| Rough-Elec/Plmb/HVAC | 3/23/2023 | Corrections Issued | KIM BEAUCHAMP |
| BUILDING-Rough-Frame | 5/4/2023 | Approved | BRYAN MEYER |
| Green Building Rough | 5/4/2023 | Approved | BRYAN MEYER |
| Rough-Elec/Plmb/HVAC | 5/4/2023 | Partial Approval | BRYAN MEYER |
| ELECTRICAL-Rough | 5/11/2023 | Approved | BRYAN MEYER |
| Insulation | 5/11/2023 | Approved | SCOTT SHUSTER |
| Drywall Nailing | 5/23/2023 | Approved | BRYAN MEYER |
| Insulation | 5/23/2023 | Approved | BRYAN MEYER |
| Interior/Exterior Lathing | 5/23/2023 | Partial Approval | BRYAN MEYER |
| Shower Pan | 6/30/2023 | Approved | BRYAN MEYER |
| Interior/Exterior Lathing | 7/6/2023 | Partial Approval | SCOTT SHUSTER |
| Interior/Exterior Lathing | 7/7/2023 | Approved | DAVID HICKMAN |
| ELECTRICAL-Final | 11/29/2023 | Not Ready for Inspection | BRYAN MEYER |
| Final | 11/29/2023 | Not Ready for Inspection | BRYAN MEYER |
| Footing/Foundation/Slab | 11/29/2023 | Approved | BRYAN MEYER |
| Green Building Final | 11/29/2023 | Approved | BRYAN MEYER |
| HVAC-Final | 11/29/2023 | Not Ready for Inspection | BRYAN MEYER |
| PLUMBING-Final | 11/29/2023 | Not Ready for Inspection | BRYAN MEYER |
| SGSOV-Seismic Gas S/O Valve | 11/29/2023 | SGSOV Approved | BRYAN MEYER |
| Smoke Detectors | 11/29/2023 | Not Ready for Inspection | BRYAN MEYER |
| ELECTRICAL-Final | 1/2/2024 | Partial Inspection | BRYAN MEYER |
| HVAC-Final | 1/2/2024 | Partial Inspection | BRYAN MEYER |
| PLUMBING-Final | 1/2/2024 | Partial Inspection | BRYAN MEYER |
| ELECTRICAL-Final | 1/17/2024 | Approved | BRYAN MEYER |
| HVAC-Final | 1/17/2024 | Approved | BRYAN MEYER |
| PLUMBING-Final | 1/17/2024 | Approved | BRYAN MEYER |
| Final | 1/29/2024 | OK to Issue CofO | BRYAN MEYER |
| Smoke Detectors | 1/29/2024 | Approved | BRYAN MEYER |