14606 W OTSEGO ST 91403
Certificate Information: 14606 W OTSEGO ST 91403
- Application / Permit
- 21014-20000-05779
- Plan Check / Job No.
- B21VN15928
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 10'-11" X 25'-10' ADDITION & NEW 9'-9" X 25'-10" COVERED PATIO TO (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 8/11/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | SERGIO MUNIZ |
| Corrections Issued | 11/25/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 12/28/2021 | SERGIO MUNIZ |
| Building Plans Picked Up | 1/3/2022 | APPLICANT |
| Plan Check Approved | 1/19/2022 | SERGIO MUNIZ |
| Issued | 8/11/2022 | APPLICANT |
| CofO in Progress | 9/20/2023 | MISAEL ESPARZA |
| No Progress | 10/17/2023 | RUBEN SALAS |
| CofO in Progress | 11/16/2023 | RUBEN SALAS |
| CofO Issued | 11/16/2023 | RUBEN SALAS |
| Permit Finaled | 11/16/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/10/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | P F I Construction Inc; Lic. No.: 1032307-B | 4717 ROCKLAND PLACE LA CANADA, CA 91011 |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/11/2022 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 11/15/2022 | Corrections Issued | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 11/29/2022 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 12/7/2022 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 12/21/2022 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 12/21/2022 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2023 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 1/30/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 3/1/2023 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 3/1/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 3/1/2023 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Not Ready for Inspection | JOHN COLEMAN |
| HVAC-Rough | 3/8/2023 | Approved | JOHN COLEMAN |
| Wood Frame | 3/8/2023 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Rough | 3/14/2023 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2023 | Approved | THOMAS FINNILA |
| HVAC-Rough | 3/14/2023 | Approved | THOMAS FINNILA |
| Wood Frame | 3/14/2023 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/17/2023 | Approved | THOMAS FINNILA |
| Green Building Rough | 3/17/2023 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/17/2023 | Corrections Issued | THOMAS FINNILA |
| Insulation | 3/20/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/20/2023 | Partial Approval | THOMAS FINNILA |
| Insulation | 3/21/2023 | Approved | JOHN COLEMAN |
| Drywall Nailing | 3/29/2023 | Approved | JOHN COLEMAN |
| ELECTRICAL-Final | 7/20/2023 | No Access for Inspection | THOMAS FINNILA |
| HVAC-Final | 7/20/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 7/20/2023 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 8/24/2023 | Approved | THOMAS FINNILA |
| Final | 8/24/2023 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 8/24/2023 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Final | 8/24/2023 | Approved | THOMAS FINNILA |
| Final | 9/19/2023 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 9/19/2023 | Approved | MISAEL ESPARZA |
| HVAC-Final | 9/19/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 9/19/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 9/19/2023 | Approved | MISAEL ESPARZA |