14606 W OTSEGO ST 91403

Certificate Information: 14606 W OTSEGO ST 91403

Application / Permit
21014-20000-05779
Plan Check / Job No.
B21VN15928
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
10'-11" X 25'-10' ADDITION & NEW 9'-9" X 25'-10" COVERED PATIO TO (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 8/11/2022
Issuing Office
Metro
Current Status
CofO Issued on 11/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 SERGIO MUNIZ
Corrections Issued 11/25/2021 SERGIO MUNIZ
Applicant returned to address corrections 12/28/2021 SERGIO MUNIZ
Building Plans Picked Up 1/3/2022 APPLICANT
Plan Check Approved 1/19/2022 SERGIO MUNIZ
Issued 8/11/2022 APPLICANT
CofO in Progress 9/20/2023 MISAEL ESPARZA
No Progress 10/17/2023 RUBEN SALAS
CofO in Progress 11/16/2023 RUBEN SALAS
CofO Issued 11/16/2023 RUBEN SALAS
Permit Finaled 11/16/2023 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/10/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 12/13/2021 JOSE DUARTE-DIAZ

Contact Information

Contractor P F I Construction Inc; Lic. No.: 1032307-B 4717 ROCKLAND PLACE      LA CANADA, CA 91011
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/11/2022 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 11/15/2022 Corrections Issued MISAEL ESPARZA
Deputy Drilled-In Anchors 11/29/2022 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 12/7/2022 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 12/21/2022 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 12/21/2022 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/26/2023 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 1/30/2023 Corrections Issued CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 1/30/2023 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 3/1/2023 Corrections Issued THOMAS FINNILA
HVAC-Rough 3/1/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 3/1/2023 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/8/2023 Not Ready for Inspection JOHN COLEMAN
HVAC-Rough 3/8/2023 Approved JOHN COLEMAN
Wood Frame 3/8/2023 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 3/14/2023 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/14/2023 Approved THOMAS FINNILA
HVAC-Rough 3/14/2023 Approved THOMAS FINNILA
Wood Frame 3/14/2023 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 3/17/2023 Approved THOMAS FINNILA
Green Building Rough 3/17/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 3/17/2023 Corrections Issued THOMAS FINNILA
Insulation 3/20/2023 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 3/20/2023 Partial Approval THOMAS FINNILA
Insulation 3/21/2023 Approved JOHN COLEMAN
Drywall Nailing 3/29/2023 Approved JOHN COLEMAN
ELECTRICAL-Final 7/20/2023 No Access for Inspection THOMAS FINNILA
HVAC-Final 7/20/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 7/20/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 8/24/2023 Approved THOMAS FINNILA
Final 8/24/2023 Corrections Issued THOMAS FINNILA
HVAC-Final 8/24/2023 Corrections Issued THOMAS FINNILA
PLUMBING-Final 8/24/2023 Approved THOMAS FINNILA
Final 9/19/2023 OK to Issue CofO MISAEL ESPARZA
Green Building Final 9/19/2023 Approved MISAEL ESPARZA
HVAC-Final 9/19/2023 Approved MISAEL ESPARZA
PLUMBING-Final 9/19/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/19/2023 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 9/19/2023 Approved MISAEL ESPARZA