8613 N MOREHART AVE 91352
Certificate Information: 8613 N MOREHART AVE 91352
- Application / Permit
- 21014-20000-05730
- Plan Check / Job No.
- B21VN15742
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 17'9" X 12'5"ADDITION TO THE (E) SFD TO CREATE NEW FAMILY ROOM , BATHROOM , ENCLOSE 2'6" X 12'8" ROOF OVERHANG TO LIVABLE SPACE AS PORTION OF THE DEN , ALL WORK PER WFPP
- Permit Issued
- Issued on 3/30/2022
- Issuing Office
- Current Status
- CofO Issued on 3/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2021 | RARES BODEA |
| Corrections Issued | 11/22/2021 | RARES BODEA |
| Applicant returned to address corrections | 3/22/2022 | RARES BODEA |
| Plan Check Approved | 3/29/2022 | RARES BODEA |
| Issued | 3/30/2022 | APPLICANT |
| Building Plans Picked Up | 5/26/2022 | APPLICANT |
| CofO in Progress | 3/3/2023 | MATTHEW NELSON |
| CofO Issued | 3/21/2023 | MICHAEL SMITH |
| Permit Finaled | 3/21/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 3/2/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 3/2/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/18/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 5/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 6/13/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 6/13/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 7/11/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 7/11/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 7/11/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 7/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 7/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 7/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 7/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 7/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 7/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 8/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 8/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 2/17/2023 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 2/17/2023 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/17/2023 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 2/17/2023 | Approved | MATTHEW NELSON |
| Final | 2/27/2023 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 2/27/2023 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/27/2023 | SGSOV Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 3/2/2023 | Approved | MATTHEW NELSON |
| Final | 3/2/2023 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 3/2/2023 | Approved | MATTHEW NELSON |
| HVAC-Final | 3/2/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 3/2/2023 | Approved | MATTHEW NELSON |