7052 N CALHOUN AVE 91405
Certificate Information: 7052 N CALHOUN AVE 91405
- Application / Permit
- 21014-20000-05726
- Plan Check / Job No.
- B21VN15725
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 19'-9" X 22'-3" DETACHED GARAGE AND 20'-3" X 40'-3" STORAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) WITH 4' X 5' PORCH ADDITION. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/11/2022
- Issuing Office
- Current Status
- CofO Issued on 8/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | RAPHAEL ROSAS |
| Corrections Issued | 11/25/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/27/2021 | RAPHAEL ROSAS |
| Issued | 1/11/2022 | APPLICANT |
| Building Plans Picked Up | 1/18/2022 | APPLICANT |
| CofO in Progress | 8/29/2022 | RICHARD DOCKUS |
| Permit Finaled | 8/30/2022 | DANIEL ORRANTE |
| CofO Issued | 8/30/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/30/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/29/2021 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 11/29/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 11/29/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2021 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 12/27/2021 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/14/2022 | Partial Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 2/24/2022 | Approved | RICHARD DOCKUS |
| Gas Test | 2/24/2022 | Partial Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 3/21/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/21/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/29/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 3/29/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 4/1/2022 | Corrections Issued | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Partial Approval | ALAN MORELOS |
| PLUMBING-Rough | 4/1/2022 | Approved | ALAN MORELOS |
| HVAC-Rough | 4/6/2022 | Corrections Issued | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 4/12/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 4/12/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Rough | 4/12/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Insulation | 4/12/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 4/15/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 4/15/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/19/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 4/19/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 4/19/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/19/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/21/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/21/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 4/21/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/21/2022 | Partial Approval | JENNIFER RABUCHIN |
| Shower Pan | 4/21/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 4/26/2022 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 6/29/2022 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Final | 6/29/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 6/29/2022 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 6/29/2022 | Approved | RICHARD DOCKUS |
| Gas Test | 7/6/2022 | Corrections Issued | DEANDRE HOFFMAN |
| HVAC-Final | 7/6/2022 | Corrections Issued | DEANDRE HOFFMAN |
| HVAC-Final | 7/11/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 7/26/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 7/26/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 8/1/2022 | Corrections Issued | RICHARD DOCKUS |
| Final | 8/12/2022 | Corrections Issued | RICHARD DOCKUS |
| Final | 8/22/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 8/26/2022 | OK to Issue CofO | RICHARD DOCKUS |