4530 N GREENBUSH AVE 91423
Certificate Information: 4530 N GREENBUSH AVE 91423
- Application / Permit
- 21014-20000-05719
- Plan Check / Job No.
- B21VN15695
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 5'-9.5" x 29'-9.5" ADDITION AT FRONT, 14'-2.5" x 21'-9.5" AND 20'-8.5" x 44'-10.5" ADDITION AT REAR AND MAJOR REMODEL TO THE (E) SINGLE FAMILY DWELLING. " NFPA 13-D FIRE SPRINKLERS THRU-OUT ".
- Permit Issued
- Issued on 5/18/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 12/1/2021 | SARKIS HARABEDIAN |
| Quality Review Completed | 12/10/2021 | STEVEN KIM |
| Applicant returned to address corrections | 1/31/2022 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 3/14/2022 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 4/4/2022 | APPLICANT |
| Applicant returned to address corrections | 4/14/2022 | SARKIS HARABEDIAN |
| Plan Check Approved | 5/10/2022 | SARKIS HARABEDIAN |
| Issued | 5/18/2022 | APPLICANT |
| CofO in Progress | 2/28/2024 | MISAEL ESPARZA |
| Permit Finaled | 3/26/2024 | DANIEL ORRANTE |
| CofO Issued | 3/26/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/26/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/18/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 4/1/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 4/5/2022 | DAGOVERTO GUERRERO |
| ZI | Cleared | 4/8/2022 | STEVEN WECHSLER |
Contact Information
| Architect | Mechur,, Ralph Steven; Lic. No.: C11683 | 3400 AIRPORT AVE 5 SANTA MONICA, CA 90405 |
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/23/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 7/5/2022 | Partial Approval | MISAEL ESPARZA |
| Wood Frame | 7/5/2022 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2022 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/26/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 9/26/2022 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 9/26/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 9/26/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 9/26/2022 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2022 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/31/2022 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/31/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 10/31/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 10/31/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 10/31/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/4/2022 | Approved | MISAEL ESPARZA |
| Insulation | 11/4/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 11/4/2022 | Approved | MISAEL ESPARZA |
| Insulation | 11/22/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/22/2022 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 11/22/2022 | Corrections Issued | MISAEL ESPARZA |
| Wood Frame | 11/22/2022 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/21/2022 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 12/21/2022 | Approved | MISAEL ESPARZA |
| Green Building Rough | 12/21/2022 | Approved | MISAEL ESPARZA |
| Shower Pan | 12/21/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/28/2022 | Approved | MISAEL ESPARZA |
| Special/Order Compliance | 5/30/2023 | Approved | JOHN COLEMAN |
| PLUMBING-Final | 10/25/2023 | Corrections Issued | MISAEL ESPARZA |
| Final | 10/31/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 10/31/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 10/31/2023 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 10/31/2023 | Corrections Issued | MISAEL ESPARZA |
| Final | 12/14/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 12/14/2023 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 12/14/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 1/10/2024 | Corrections Issued | MISAEL ESPARZA |
| Smoke Detectors | 1/10/2024 | Approved | MISAEL ESPARZA |
| Final | 2/22/2024 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 2/27/2024 | Approved | MISAEL ESPARZA |