17184 W RINALDI ST 91344

Certificate Information: 17184 W RINALDI ST 91344

Application / Permit
21014-20000-05711
Plan Check / Job No.
B21VN15682
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 2ND STORY ADDITION TO (E) GARAGE AND CONVERT THE ENTIRE BUILDING TO 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 2/18/2022
Issuing Office
Current Status
CofO Issued on 3/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 DANIEL YIP
Corrections Issued 12/21/2021 DANIEL YIP
Quality Review Completed 12/22/2021 LIPING TENG
Plan Check Approved 2/8/2022 DANIEL YIP
Issued 2/18/2022 APPLICANT
CofO in Progress 10/31/2022 JOHN JANSON
Permit Finaled 3/10/2023 JOHN JANSON
CofO Issued 3/10/2023 JOHN JANSON
Permit Finaled 3/10/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/10/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 1/10/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 1/21/2022 PATRICK MISCHLICH
Eng Process Fee Ord 176,300 Cleared 1/24/2022 CARLOS AGUILERA
Sewer availability Cleared 1/24/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/17/2022 Partial Approval DAVID SCANTLIN
Deputy Drilled-In Anchors 5/23/2022 Conditional Approval KRISTEN CAUSEY
Excavation/Setback/Form/Re-Bar 5/24/2022 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 8/8/2022 No Access for Inspection KRISTEN CAUSEY
Gas Test 8/8/2022 Corrections Issued KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 8/11/2022 Conditional Approval DAVID SCANTLIN
Gas Test 8/11/2022 Partial Approval DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 8/16/2022 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 8/22/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 8/22/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 8/30/2022 Approved DAVID SCANTLIN
Green Building Rough 8/30/2022 Approved DAVID SCANTLIN
Interior/Exterior Lathing 8/30/2022 Partial Inspection DAVID SCANTLIN
MERV13>=Rough 8/30/2022 Approved DAVID SCANTLIN
Drywall Nailing 9/6/2022 Approved KRISTEN CAUSEY
Final 10/5/2022 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 10/5/2022 Approved DAVID SCANTLIN
Green Building Final 10/5/2022 Not Ready for Inspection DAVID SCANTLIN
MERV13>=Final 10/5/2022 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 10/5/2022 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 10/5/2022 Approved DAVID SCANTLIN
Final 10/27/2022 OK to Issue CofO DAVID SCANTLIN
Green Building Final 10/27/2022 Approved DAVID SCANTLIN