657 E 118TH PL 90059

Certificate Information: 657 E 118TH PL 90059

Application / Permit
21014-20000-05707
Plan Check / Job No.
B21VN15673
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 20' DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 9/26/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 GURUNATH NESARAJAH
Corrections Issued 11/27/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 4/16/2022 GURUNATH NESARAJAH
Building Plans Picked Up 4/20/2022 APPLICANT
Plan Check Approved 9/22/2022 ANGELICA MARTINEZ
Issued 9/26/2022 APPLICANT
CofO in Progress 1/11/2024 JOHN KLARIN
Permit Finaled 1/11/2024 ANSON MAGLASANG
CofO Issued 1/11/2024 ANSON MAGLASANG
Permit Finaled 1/11/2024 ANSON MAGLASANG

Permit Application Clearance Information

Construction near power lines Cleared 3/19/2022 RIDWAN HARDY
Address approval Cleared 3/24/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 3/24/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/29/2022 JEANIE LAM
Sewer availability Cleared 3/29/2022 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/28/2022 Partial Approval JOHN KLARIN
Underground Mechanical 10/28/2022 Partial Approval JOHN KLARIN
Underground Mechanical 10/31/2022 Partial Approval JOHN KLARIN
Deputy Drilled-In Anchors 11/15/2022 Approved JOHN KLARIN
Footing/Foundation/Slab 11/29/2022 Corrections Issued ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 12/6/2022 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 12/14/2022 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 1/9/2023 Approved JAMES CHAVEZ
Green Building Rough 1/9/2023 Not Ready for Inspection JAMES CHAVEZ
MERV13>=Rough 1/9/2023 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Rough 2/2/2023 Approved JOHN KLARIN
PLUMBING-Rough 2/2/2023 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 2/7/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 2/7/2023 Approved JOHN KLARIN
PLUMBING-Rough 2/7/2023 Approved JOHN KLARIN
Insulation 2/9/2023 Approved JOHN KLARIN
Drywall Nailing 2/13/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 4/18/2023 Corrections Issued JAMES CHAVEZ
Shower Pan 4/18/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 4/21/2023 Approved JAMES CHAVEZ
ELECTRICAL-Rough 4/28/2023 Corrections Issued JAMES CHAVEZ
BUILDING-Rough-Frame 7/5/2023 Approved JOHN KLARIN
Final 7/5/2023 Corrections Issued JOHN KLARIN
Green Building Final 7/5/2023 Approved JOHN KLARIN
Green Building Rough 7/5/2023 Approved JOHN KLARIN
MERV13>=Final 7/5/2023 Approved JOHN KLARIN
MERV13>=Rough 7/5/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 7/5/2023 SGSOV Not Ready JOHN KLARIN
Smoke Detectors 7/5/2023 Approved JOHN KLARIN
Final 8/4/2023 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 8/4/2023 SGSOV Approved JOHN KLARIN
ELECTRICAL-Final 9/18/2023 Approved JOHN KLARIN
Final 9/18/2023 Corrections Issued JOHN KLARIN
HVAC-Final 9/18/2023 Approved JOHN KLARIN
PLUMBING-Final 9/18/2023 Approved JOHN KLARIN
Final 11/6/2023 Corrections Issued JOHN KLARIN
Final 12/19/2023 Corrections Issued JOHN KLARIN
Final 1/11/2024 OK to Issue CofO JOHN KLARIN