- PROPOSED ADDITION AND MAJOR REMODEL TO (E) SFD W/ NEW 2-CAR GARAGE. NFPA 13D SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 3/21/2022
- Issuing Office
- Current Status
- CofO Issued on 10/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | RAPHAEL ROSAS |
| Corrections Issued | 11/30/2021 | RAPHAEL ROSAS |
| Quality Review Completed | 12/8/2021 | STEVEN KIM |
| Building Plans Picked Up | 12/9/2021 | APPLICANT |
| Plan Check Approved | 3/14/2022 | RAPHAEL ROSAS |
| Issued | 3/21/2022 | APPLICANT |
| CofO in Progress | 8/21/2023 | KIRK SANDERS |
| Permit Finaled | 10/18/2023 | RUBEN SALAS |
| CofO Issued | 10/18/2023 | RUBEN SALAS |
| Permit Finaled | 10/18/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/16/2021 | CARLOS AGUILERA |
| Permit | Cleared | 12/16/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/20/2021 | CARLOS AGUILERA |
| Specific Plan | Cleared | 12/20/2021 | ERIN NASH |
| ZA Case | Cleared | 12/20/2021 | ERIN NASH |
| ZI | Cleared | 12/20/2021 | ERIN NASH |
| ZI | Cleared | 12/20/2021 | ERIN NASH |
| Trees in Parkway | Cleared | 1/25/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 3/3/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/4/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | J J P Construction Inc; Lic. No.: 960864-B | 12555 VANOWEN STREET 2ND FLOOR OFC NORTH HOLLYWOOD, CA 91605 |
| Engineer | Warling,, Jeffrey Paul; Lic. No.: C43743 | 1792 PEREGRINE CT SIMI VALLEY, CA 93065 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/27/2022 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 4/27/2022 | Approved | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 8/31/2022 | Approved | RAFAEL CORTES |
| Footing/Foundation/Slab | 8/31/2022 | Partial Approval | RAFAEL CORTES |
| Underground Mechanical | 9/7/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 9/8/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Pre-Inspection | 9/8/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Pre-Inspection | 9/9/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Underground Mechanical | 9/9/2022 | Partial Approval | RAFAEL CORTES |
| Footing/Foundation/Slab | 9/13/2022 | Approved | RAFAEL CORTES |
| Pre-Inspection | 9/13/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Underground Mechanical | 9/13/2022 | Partial Approval | RAFAEL CORTES |
| Pre-Inspection | 9/14/2022 | Not Ready for Inspection | RAFAEL CORTES |
| PLUMBING-Rough | 9/20/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Not Ready for Inspection | RAFAEL CORTES |
| PLUMBING-Rough | 9/22/2022 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2022 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Partial Approval | RAFAEL CORTES |
| Deputy Wood Construction | 11/14/2022 | Conditional Approval | MICHAEL SMITH |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 12/21/2022 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 1/5/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 1/5/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 1/5/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 1/12/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 1/20/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 1/20/2023 | Approved | KIRK SANDERS |
| Shower Pan | 1/20/2023 | Approved | KIRK SANDERS |
| Insulation | 2/3/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 2/3/2023 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 2/10/2023 | Approved | KIRK SANDERS |
| HVAC-Final | 6/27/2023 | Corrections Issued | KIRK SANDERS |
| Pre-Inspection | 6/27/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 6/29/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 6/29/2023 | Corrections Issued | KIRK SANDERS |
| Final | 7/3/2023 | Corrections Issued | KIRK SANDERS |
| Gas Test | 7/3/2023 | Approved | KIRK SANDERS |
| Green Building Final | 7/3/2023 | Approved | KIRK SANDERS |
| Pre-Inspection | 7/3/2023 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 7/3/2023 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 7/3/2023 | Approved | KIRK SANDERS |
| Final | 7/31/2023 | Partial Approval | KIRK SANDERS |
| PLUMBING-Final | 7/31/2023 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 7/31/2023 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 7/31/2023 | Not Ready for Inspection | KIRK SANDERS |
| Final | 8/14/2023 | Corrections Issued | KIRK SANDERS |
| Final | 8/18/2023 | OK to Issue CofO | KIRK SANDERS |