6910 N DE CELIS PL 91406

Certificate Information: 6910 N DE CELIS PL 91406

Application / Permit
21014-20000-05666
Plan Check / Job No.
B21VN15548
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (10'-1"x9'-7"), 100 S.F. ADDITION AND NEW FRONT COVERED PORCH 97 SQFT) W/ A CONCRETE RAMP TO THE SFD PER WFPP
Permit Issued
Issued on 12/17/2021
Issuing Office
Current Status
CofO Issued on 5/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/11/2021 APPLICANT
Assigned to Plan Check Engineer 11/12/2021 PETER MOSESIAN
Corrections Issued 11/12/2021 PETER MOSESIAN
Building Plans Picked Up 11/19/2021 APPLICANT
Plan Check Approved 12/15/2021 PETER MOSESIAN
Issued 12/17/2021 APPLICANT
CofO in Progress 5/19/2022 RAUL OLAGI
Permit Finaled 5/25/2022 RONALD MYRICK
CofO Issued 5/25/2022 RONALD MYRICK
Permit Finaled 5/25/2022 RONALD MYRICK

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/30/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 12/10/2021 JOSE DUARTE-DIAZ

Contact Information

Contractor Castle Remodeling; Lic. No.: 852398-B 5280 KANAN ROAD      AGOURA HILLS, CA 91301

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/7/2022 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 1/10/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Partial Approval RAUL OLAGI
Green Building Rough 1/13/2022 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/18/2022 Partial Approval RAUL OLAGI
Insulation 1/18/2022 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 1/31/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/31/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 2/4/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/4/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 2/15/2022 Approved ALAN MORELOS
BUILDING-Rough-Frame 2/22/2022 Approved RAUL OLAGI
Green Building Rough 2/22/2022 Approved RAUL OLAGI
Insulation 3/3/2022 Approved ALAN MORELOS
Special/Order Compliance 3/3/2022 Corrections Issued ALAN MORELOS
Drywall Nailing 3/10/2022 Corrections Issued ALAN MORELOS
Drywall Nailing 3/16/2022 Approved ALAN MORELOS
Insulation 3/16/2022 Approved ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 4/25/2022 SGSOV Not Ready RAUL OLAGI
Final 5/6/2022 Corrections Issued RAUL OLAGI
Green Building Final 5/6/2022 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/6/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 5/6/2022 Approved RAUL OLAGI
Final 5/18/2022 Corrections Issued RAUL OLAGI
Final 5/19/2022 OK to Issue CofO RAUL OLAGI