11623-11625 W HAYNES ST 91606
Certificate Information: 11623-11625 W HAYNES ST 91606
- Application / Permit
- 21014-20000-05650
- Plan Check / Job No.
- B21VN15474
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 50'-2" X 39'-2" IRREGULAR SHAPED FIRST STORY ADDITION TO ENLARGE DWELLING (1792 SQ FT); ADD 49'-4" X 42'-9" SECOND UNIT ABOVE (1897 SQ FT); EQUIPPED WITH NFPA 3-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 5/10/2022
- Issuing Office
- Current Status
- CofO Issued on 12/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | SELLA BENYAMIN |
| Corrections Issued | 11/30/2021 | SELLA BENYAMIN |
| Quality Review Completed | 12/8/2021 | STEVEN KIM |
| Building Plans Picked Up | 12/13/2021 | APPLICANT |
| Applicant returned to address corrections | 4/21/2022 | SELLA BENYAMIN |
| Plan Check Approved | 5/10/2022 | SELLA BENYAMIN |
| Issued | 5/10/2022 | APPLICANT |
| CofO in Progress | 9/1/2023 | JOHN HAYES |
| No Progress | 11/11/2023 | ROBERT GOLD |
| CofO in Progress | 11/11/2023 | ROBERT GOLD |
| CofO in Progress | 11/22/2023 | ROBERT GOLD |
| No Progress | 12/6/2023 | ROBERT GOLD |
| CofO in Progress | 12/8/2023 | ROBERT GOLD |
| CofO Issued | 12/19/2023 | RUBEN SALAS |
| Permit Finaled | 12/19/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development | Cleared | 3/29/2022 | KHAING AYE |
| Address approval | Cleared | 4/5/2022 | CHRIS CHAHBAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2022 | CHRIS CHAHBAZ |
| Roof/Waste drainage to street | Cleared | 4/6/2022 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 4/6/2022 | CHRIS CHAHBAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/27/2022 | Corrections Issued | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 6/13/2022 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 7/12/2022 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 7/12/2022 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 7/12/2022 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/19/2022 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 7/19/2022 | Partial Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/21/2022 | Approved | JOHN HAYES |
| Pre-Inspection | 8/11/2022 | Not Ready for Inspection | JOHN HAYES |
| Pre-Inspection | 8/17/2022 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2022 | Partial Approval | ALAN MORELOS |
| Insulation | 8/25/2022 | Partial Approval | JOHN HAYES |
| Pre-Inspection | 8/31/2022 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 9/2/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 9/21/2022 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2022 | Corrections Issued | JOHN HAYES |
| Special/Order Compliance | 10/21/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 10/27/2022 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2022 | Partial Approval | JOHN HAYES |
| Green Building Rough | 10/27/2022 | Partial Approval | JOHN HAYES |
| Wood Frame | 10/27/2022 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 10/28/2022 | Approved | JOHN HAYES |
| Sewer | 10/28/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 11/15/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 11/15/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 11/23/2022 | Conditional Approval | THOMAS FINNILA |
| HVAC-Rough | 11/23/2022 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 11/30/2022 | Approved | JOHN HAYES |
| Pre-Inspection | 11/30/2022 | Partial Approval | JOHN HAYES |
| Verify Sprinkler Sign Off | 11/30/2022 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 12/27/2022 | Approved | JOHN HAYES |
| Green Building Rough | 12/27/2022 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 12/27/2022 | Approved | JOHN HAYES |
| Insulation | 1/4/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Insulation | 1/9/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 1/23/2023 | Approved | JOHN HAYES |
| Shower Pan | 2/3/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 3/2/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 6/21/2023 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 6/21/2023 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Final | 6/21/2023 | Corrections Issued | THOMAS FINNILA |
| Service/Power Release | 6/26/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 8/28/2023 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 8/28/2023 | Approved | JOHN HAYES |
| Green Building Final | 8/28/2023 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 8/28/2023 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 8/28/2023 | Approved | JOHN HAYES |
| Final | 9/1/2023 | Conditional Approval | JOHN HAYES |
| Service/Power Release | 9/1/2023 | Approved | JOHN HAYES |
| Special/Order Compliance | 11/14/2023 | Corrections Issued | JOHN HAYES |