6624 N LANKERSHIM BLVD 91606
Certificate Information: 6624 N LANKERSHIM BLVD 91606
- Application / Permit
- 21014-20000-05648
- Plan Check / Job No.
- B21VN15469
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (9) Car Wash
- Work Description
- REMOVE HAND DETAIL AREA AND ADD 9'0" X 78'0" IRREGULAR SHAPED AND 8'10" X 9'0" ADDITIONS TO (E) CARWASH (NO EXPANSION TO TUNNEL) TO ENLARGE OFFICE & EQUIPMENT ROOM, NEW ELECTRICAL ROOM, AND NEW RESTROOMS. SEE COMMENTS
- Permit Issued
- Issued on 9/28/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | MARVEL DELACRUZ |
| Corrections Issued | 12/3/2021 | MARVEL DELACRUZ |
| Quality Review Completed | 12/10/2021 | STEVEN KIM |
| Building Plans Picked Up | 12/13/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 12/13/2021 | APPLICANT |
| Green Plans Picked Up | 12/13/2021 | APPLICANT |
| Applicant returned to address corrections | 3/30/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 9/26/2022 | MARVEL DELACRUZ |
| Plan Check Approved | 9/28/2022 | MARVEL DELACRUZ |
| Issued | 9/28/2022 | APPLICANT |
| CofO in Progress | 10/30/2023 | ROBERT DAVIS |
| CofO Issued | 10/30/2023 | RICKEY JACKSON |
| Permit Finaled | 10/30/2023 | RICKEY JACKSON |
Permit Application Clearance Information
| Comm Cor/Mini-Mall | Cleared | 1/21/2022 | NELSON RODRIGUEZ |
| Comm Cor/Mini-Mall | Cleared | 1/21/2022 | NELSON RODRIGUEZ |
| Green Code | Cleared | 3/24/2022 | MICHAEL AYERS |
| DAS Clearance | Cleared | 3/29/2022 | NORLITO MEDRANO |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2022 | CARLOS AGUILERA |
| Comm Cor/Mini-Mall | Cleared | 4/4/2022 | NELSON RODRIGUEZ |
| Driveway location | Cleared | 4/7/2022 | BRANDON WILSON |
| Highway dedication | Cleared | 4/7/2022 | CARLOS AGUILERA |
| Permit | Cleared | 4/7/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/11/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 9/20/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 9/20/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Sipan Design & Development Inc; Lic. No.: 885235-B | 705 BALBOA AVENUE GLENDALE, CA 91206 |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 9/29/2022 | Partial Inspection | ROBERT DAVIS |
| Footing/Foundation/Slab | 11/1/2022 | Conditional Approval | ROBERT DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2023 | Partial Approval | ROBERT DAVIS |
| Light Gage Steel Frame | 3/28/2023 | Partial Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 5/18/2023 | Approved | ROBERT DAVIS |
| Special/Order Compliance | 8/23/2023 | Partial Inspection | ROBERT DAVIS |
| Drywall Nailing | 10/12/2023 | Approved | ROBERT DAVIS |
| Final | 10/12/2023 | OK to Issue CofO | ROBERT DAVIS |
| Green Building Final | 10/12/2023 | Approved | ROBERT DAVIS |
| Green Building Rough | 10/12/2023 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV No Gas | ROBERT DAVIS |
| Smoke Detectors | 10/12/2023 | Approved | ROBERT DAVIS |
| Wood Frame | 10/12/2023 | Approved | ROBERT DAVIS |