17643 W MARTHA ST 91316

Certificate Information: 17643 W MARTHA ST 91316

Application / Permit
21014-20000-05647
Plan Check / Job No.
B21VN15463
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FOUNDATION REPAIR AND 17'-6" x 8'-8" ADDITION AT REAR OF (E) SINGLE FAMILY DWELLING AND INTERIOR REMODEL; ALL WORK PER ENGINEERING DESIGN
Permit Issued
Issued on 4/4/2022
Issuing Office
Current Status
CofO Issued on 9/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2021 APPLICANT
Assigned to Plan Check Engineer 12/9/2021 SEAN SHAHMIRI
Corrections Issued 12/13/2021 SEAN SHAHMIRI
Quality Review Completed 12/17/2021 OMID HEDAYAT
Building Plans Picked Up 1/20/2022 APPLICANT
Plan Check Approved 3/1/2022 SEAN SHAHMIRI
Issued 4/4/2022 APPLICANT
CofO in Progress 9/2/2022 SEAN HAUPT
CofO Issued 9/21/2022 MICHAEL SMITH
Permit Finaled 9/21/2022 MICHAEL SMITH

Permit Application Clearance Information

ZI Cleared 2/15/2022 MIGUEL GAMBOA
Roof/Waste drainage to street Cleared 2/16/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 2/17/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Ha My Design Inc; Lic. No.: 999603-B 6700 FALLBROOK AVE #235      WEST HILLS, CA 91307
Engineer Hoerner,, John Brent; Lic. No.: S2145 24024 VIA CANDELA      VALENCIA, CA 91355

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Wood Construction 4/19/2022 Conditional Approval JUSTIN HAWLEY
Excavation/Setback/Form/Re-Bar 4/20/2022 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 4/20/2022 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 5/10/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 5/19/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 6/6/2022 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 6/6/2022 Approved SEAN HAUPT
Green Building Rough 6/6/2022 Approved SEAN HAUPT
MERV13>=Rough 6/6/2022 Approved SEAN HAUPT
PLUMBING-Rough 6/6/2022 Approved SEAN HAUPT
Insulation 6/17/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 6/17/2022 Approved SEAN HAUPT
Drywall Nailing 6/23/2022 Approved MORRIS JACKSON
BUILDING-Rough-Frame 8/16/2022 Approved SEAN HAUPT
Final 8/16/2022 Corrections Issued SEAN HAUPT
Green Building Final 8/16/2022 Not Ready for Inspection SEAN HAUPT
MERV13>=Final 8/16/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 8/16/2022 SGSOV Approved SEAN HAUPT
Smoke Detectors 8/16/2022 Approved SEAN HAUPT
Final 8/23/2022 Corrections Issued SEAN HAUPT
Green Building Final 8/23/2022 Not Ready for Inspection SEAN HAUPT
Final 9/1/2022 OK to Issue CofO SEAN HAUPT
Green Building Final 9/1/2022 Approved SEAN HAUPT