17624 W MARTHA ST 91316
Certificate Information: 17624 W MARTHA ST 91316
- Application / Permit
- 21014-20000-05633
- Plan Check / Job No.
- B21VN15411
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- IRREGULAR SHAPED 44'5" x 52'6" ADDITION AND MAJOR REMODEL TO EXISTING SINGLE FAMILY DWELLING TO CONSIST OF ADDING BEDROOMS, BATHROOMS, RELOCATING THE KITCHEN AND UPGRADES THROUGHOUT. NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 9/8/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 11/20/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 11/23/2021 | APPLICANT |
| Applicant returned to address corrections | 7/28/2022 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 8/16/2022 | LUIS RINCON |
| Plan Check Approved | 8/25/2022 | ANGELICA MARTINEZ |
| Issued | 9/8/2023 | APPLICANT |
| CofO in Progress | 1/3/2025 | JON MCHUGH |
| No Progress | 1/9/2025 | SEAN WIRCH |
| CofO in Progress | 1/9/2025 | SEAN WIRCH |
| Permit Finaled | 6/10/2025 | JOHN JANSON |
| CofO Issued | 6/10/2025 | JOHN JANSON |
| Permit Finaled | 6/10/2025 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 3/2/2022 | RYAN LY |
| Sewer availability | Cleared | 3/4/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 4/29/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 6/30/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Rex Contractors Inc; Lic. No.: 961316-B | 418 BAMBOO LN STE A LOS ANGELES, CA 90012 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/14/2023 | Not Ready for Inspection | JON MCHUGH |
| Footing/Foundation/Slab | 12/18/2023 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2024 | Not Ready for Inspection | JON MCHUGH |
| Gas Test | 1/8/2024 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 1/8/2024 | Not Ready for Inspection | JON MCHUGH |
| Underground Mechanical | 1/8/2024 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 1/31/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 1/31/2024 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2024 | Corrections Issued | JON MCHUGH |
| Green Building Rough | 1/31/2024 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 1/31/2024 | Not Ready for Inspection | JON MCHUGH |
| MERV13>=Rough | 1/31/2024 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 1/31/2024 | Not Ready for Inspection | JON MCHUGH |
| Verify Sprinkler Sign Off | 1/31/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 2/8/2024 | Corrections Issued | JON MCHUGH |
| Insulation | 2/8/2024 | Corrections Issued | JON MCHUGH |
| Interior/Exterior Lathing | 2/8/2024 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 2/8/2024 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 2/13/2024 | Approved | JON MCHUGH |
| HVAC-Rough | 2/13/2024 | Approved | JON MCHUGH |
| PLUMBING-Rough | 2/13/2024 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 2/21/2024 | Approved | JON MCHUGH |
| Green Building Rough | 2/21/2024 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 2/21/2024 | Partial Approval | JON MCHUGH |
| MERV13>=Rough | 2/21/2024 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 2/21/2024 | Approved | JON MCHUGH |
| Shower Pan | 2/26/2024 | Approved | DAVID SCANTLIN |
| Insulation | 2/27/2024 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 2/27/2024 | Approved | JON MCHUGH |
| Drywall Nailing | 3/6/2024 | Approved | HENRY KIM |
| Service/Power Release | 4/24/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Service/Power Release | 4/29/2024 | Approved | JON MCHUGH |
| Final | 10/10/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 10/10/2024 | Not Ready for Inspection | JON MCHUGH |
| MERV13>=Final | 10/10/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 10/10/2024 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 10/10/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 1/2/2025 | Approved | JON MCHUGH |
| Final | 1/2/2025 | OK to Issue CofO | JON MCHUGH |
| Green Building Final | 1/2/2025 | Approved | JON MCHUGH |
| HVAC-Final | 1/2/2025 | Approved | JON MCHUGH |
| PLUMBING-Final | 1/2/2025 | Approved | JON MCHUGH |