6127 N ALONZO AVE 91316

Certificate Information: 6127 N ALONZO AVE 91316

Application / Permit
21014-20000-05632
Plan Check / Job No.
B21VN15409
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
6'-8" X 21'-6" ADDITION TO (E) SFD, REMODEL, RE-FRAME AND RE-ROOF PORTION OF THE ROOF. ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 7/1/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 GURUNATH NESARAJAH
Corrections Issued 11/21/2021 GURUNATH NESARAJAH
Building Plans Picked Up 11/29/2021 APPLICANT
Applicant returned to address corrections 6/10/2024 ARAMIK SHAHMIRZAIAN
Plan Check Approved 6/27/2024 DANIEL ABRAMYAN
Issued 7/1/2024 APPLICANT
CofO in Progress 9/22/2025 MORRIS JACKSON
Permit Finaled 9/30/2025 MICHAEL PELHAM
CofO Issued 9/30/2025 MICHAEL PELHAM
Permit Finaled 9/30/2025 MICHAEL PELHAM

Permit Application Clearance Information

ZI Cleared 6/5/2024 ALEX VELA
Sewer availability Cleared 6/8/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/11/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/21/2024 CARLOS AGUILERA

Contact Information

Contractor Rex Contractors Inc; Lic. No.: 961316-B 418 BAMBOO LN STE A      LOS ANGELES, CA 90012
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/24/2024 Conditional Approval MORRIS JACKSON
Footing/Foundation/Slab 7/26/2024 Corrections Issued JON MCHUGH
Footing/Foundation/Slab 7/31/2024 Approved JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Partial Approval MORRIS JACKSON
Underground Mechanical 8/6/2024 Not Ready for Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 8/8/2024 Partial Approval MORRIS JACKSON
Insulation 8/8/2024 Partial Approval MORRIS JACKSON
PLUMBING-Rough 8/8/2024 Partial Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 8/13/2024 Partial Approval MORRIS JACKSON
ELECTRICAL-Rough 9/13/2024 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 9/13/2024 Corrections Issued MORRIS JACKSON
HVAC-Rough 9/13/2024 Approved MORRIS JACKSON
PLUMBING-Rough 9/13/2024 Approved MORRIS JACKSON
BUILDING-Rough-Frame 9/30/2024 Approved MORRIS JACKSON
Green Building Rough 9/30/2024 Approved MORRIS JACKSON
Interior/Exterior Lathing 9/30/2024 Corrections Issued MORRIS JACKSON
Shower Pan 9/30/2024 Approved MORRIS JACKSON
Insulation 10/15/2024 Approved MORRIS JACKSON
Interior/Exterior Lathing 10/15/2024 Approved MORRIS JACKSON
Special/Order Compliance 10/15/2024 Corrections Issued MORRIS JACKSON
Drywall Nailing 10/21/2024 Approved MORRIS JACKSON
Final 7/15/2025 Corrections Issued MORRIS JACKSON
Green Building Final 7/15/2025 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 7/15/2025 SGSOV Approved MORRIS JACKSON
Smoke Detectors 7/15/2025 Approved MORRIS JACKSON
Final 8/28/2025 Not Ready for Inspection MORRIS JACKSON
Final 9/2/2025 Not Ready for Inspection MORRIS JACKSON
Final 9/15/2025 Not Ready for Inspection MORRIS JACKSON
Final 9/16/2025 Corrections Issued MORRIS JACKSON
Final 9/22/2025 OK to Issue CofO MORRIS JACKSON