11508-11510 W ERWIN ST 91606
Certificate Information: 11508-11510 W ERWIN ST 91606
- Application / Permit
- 21014-20000-05586
- Plan Check / Job No.
- B21VN15271
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- CONVERT 18' X 18' ATTACHED GARAGE INTO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22 AND AN ADDITION OF 10'-1" X 11' TO REAR OF (E) SFD TO EXPAND THE (E) BEDROOM BY ADDING A BATHROOM, AND REMODELING THE KITCHECN AND LAUNDRY ROOM. ALL WORK PER WFPP.
- Permit Issued
- Issued on 2/3/2022
- Issuing Office
- Current Status
- CofO Issued on 12/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | PARISA ZAHABI |
| Corrections Issued | 11/25/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 1/19/2022 | LUISANGEL VALENZUELA |
| Plan Check Approved | 2/3/2022 | LUISANGEL VALENZUELA |
| Issued | 2/3/2022 | APPLICANT |
| Building Plans Picked Up | 2/4/2022 | APPLICANT |
| CofO in Progress | 8/23/2022 | JOHN HAYES |
| CofO Issued | 12/19/2022 | MICHAEL SMITH |
| Permit Finaled | 12/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/30/2021 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 11/30/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/1/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/9/2022 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 2/9/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/9/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/15/2022 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2022 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 3/7/2022 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/11/2022 | Partial Approval | MATT KELLERMAN |
| ELECTRICAL-Rough | 3/11/2022 | Approved | MATT KELLERMAN |
| Green Building Rough | 3/11/2022 | Not Ready for Inspection | MATT KELLERMAN |
| PLUMBING-Rough | 3/11/2022 | Approved | MATT KELLERMAN |
| Interior/Exterior Lathing | 3/24/2022 | Partial Approval | CALEB MEISTER |
| Insulation | 4/4/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/11/2022 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 5/11/2022 | Partial Approval | ASHLEY THOMPSON |
| Green Building Rough | 5/11/2022 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 5/11/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 5/11/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Shower Pan | 5/11/2022 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 5/13/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 5/13/2022 | Approved | ASHLEY THOMPSON |
| Special/Order Compliance | 7/11/2022 | No Access for Inspection | JOHN HAYES |
| Final | 8/15/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 8/15/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 8/15/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 8/15/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 8/22/2022 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 8/22/2022 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 8/22/2022 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 8/22/2022 | Approved | JOHN HAYES |