8102 N LOUISE AVE 91325
Certificate Information: 8102 N LOUISE AVE 91325
- Application / Permit
- 21014-20000-05581
- Plan Check / Job No.
- B21VN15259
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD ACCESSORY DWELLING UNIT OVER EXISTING GARAGE AND NEW PATIO COVER. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 1/10/2022
- Issuing Office
- Current Status
- CofO Issued on 3/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2021 | PINANK PATEL |
| Corrections Issued | 11/19/2021 | PINANK PATEL |
| Plan Check Approved | 1/7/2022 | PINANK PATEL |
| Issued | 1/10/2022 | APPLICANT |
| Building Plans Picked Up | 1/13/2022 | APPLICANT |
| CofO in Progress | 2/15/2024 | RAUL OLAGI |
| Permit Finaled | 3/20/2024 | RUBEN SALAS |
| CofO Issued | 3/20/2024 | RUBEN SALAS |
| Permit Finaled | 3/20/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/23/2021 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 11/23/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/1/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Engineer | Kator,, Khaled; Lic. No.: C69781 | 19519 TULSA ST NORTHRIDGE, CA 91326 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/20/2022 | Corrections Issued | ALAN MORELOS |
| PLUMBING-Rough | 7/20/2022 | Partial Approval | ALAN MORELOS |
| Underground Mechanical | 7/20/2022 | Approved | ALAN MORELOS |
| Footing/Foundation/Slab | 7/27/2022 | Not Ready for Inspection | ALAN MORELOS |
| Footing/Foundation/Slab | 9/7/2022 | Corrections Issued | RAUL OLAGI |
| Special/Order Compliance | 9/7/2022 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/20/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 9/20/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 9/20/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 9/20/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/2/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 10/2/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 10/2/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 10/2/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 10/23/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 10/23/2023 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2023 | Partial Approval | RAUL OLAGI |
| HVAC-Rough | 10/23/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 10/23/2023 | Approved | RAUL OLAGI |
| Insulation | 11/13/2023 | Not Ready for Inspection | RAUL OLAGI |
| Interior/Exterior Lathing | 11/13/2023 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/20/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 11/20/2023 | Approved | RAUL OLAGI |
| Insulation | 11/20/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 11/20/2023 | Partial Approval | RAUL OLAGI |
| Drywall Nailing | 12/1/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 12/1/2023 | Approved | RAUL OLAGI |
| Final | 2/1/2024 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 2/1/2024 | Approved | RAUL OLAGI |
| Green Building Final | 2/1/2024 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 2/1/2024 | SGSOV Not Ready | RAUL OLAGI |
| Smoke Detectors | 2/1/2024 | Approved | RAUL OLAGI |
| Final | 2/14/2024 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 2/14/2024 | SGSOV Approved | RAUL OLAGI |
| Final | 2/15/2024 | OK to Issue CofO | RAUL OLAGI |